offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Seajacks Vessels Install 36 Turbines at Walney 2 Offshore Wind Farm (UK)
Operations & Maintenance

August 11, 2011 · about 15 years ago

Seajacks Vessels Install 36 Turbines at Walney 2 Offshore Wind Farm (UK)

The Seajacks vessels continue to work in tandem, installing Siemens 3.6MW WTGs at a rapid pace on Walney 2 Offshore Wind Farm. Recent installation activities have been described as “booming” by client Dong Energy. 155 turbines now installed – 7 turbines installed in the past week Seajacks Operations

1 minutes read
  • LinkedIn
  • X
  • Email

The Seajacks vessels continue to work in tandem, installing Siemens 3.6MW WTGs at a rapid pace on Walney 2 Offshore Wind Farm. Recent installation activities have been described as “booming” by client Dong Energy.

155 turbines now installed – 7 turbines installed in the past week

Seajacks Operations Manager, Wes McDonald says “So far at Walney 2, we’ve installed 36 turbines. Kraken and Leviathan have installed 18 each. Both the Seajacks Kraken and Seajacks Leviathan are performing efficiently and effectively during this period of intense installation activity.

This takes the total number of turbines installed by Seajacks to 155. This past week we installed 7 turbines in 7 days. A great achievement by all the team onboard the vessels.”

DONG Energy has elected to install the WTGs and cables in parallel in order to shorten the overall construction timeframe.

In 2010, Seajacks Kraken installed 46 of a total of 51 turbines at Walney 1 Offshore Wind Farm, which are now producing clean, renewable energy for the UK.

[mappress]

Source: seajacks, August 11, 2011

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Operations & Maintenance

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Young Oysters Deployed on Two North Sea Cable Crossings
  2. 2Pacifico Energy Unveils EUR 860+ Million Investment in Two Offshore Wind Projects in South Korea
  3. 3Fourth Vard-Built CSOV Joins Windward Offshore Fleet
  4. 4ABS to Support Japanese Company’s 18 MW Floating Wind Turbine Pilot in Brazil

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free