MPI Discovery Undocks in COSCO Nantong Shipyard (China)

 

On July 24, the second wind turbine installation vessel was successfully undocked in COSCO Nantong Shipyard.

Whilst the vessel was in dock, the yard completed the installation of six pile legs and the lifting cylinder, the installation and commissioning of hydraulic piping systems andthe load testing of its six generators. COSCO Nantong Shipyard continues to optimize the construction process and improve efficiency with innovative technological solutions.

After undocking, the commissioning of pile legs, main crane and the other systems will be carried out to make preparations for the sea trials.

[mappress]

Source: cosco-shipyard, September 22, 2011