Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›New Scira O&M Base Construction Progresses at North Norfolk, UK
Operations & Maintenance

June 22, 2012 · about 14 years ago

New Scira O&M Base Construction Progresses at North Norfolk, UK

One of the owners of North Norfolk’s Walsingham Estate placed the first stone in the wall of Scira’s operational base at a small ceremony to mark a key stage in the building’s construction. The laying of the stone by Elizabeth Meath Baker was carried out on Tuesday 19th June 2012 at the construction

2 minutes read
  • LinkedIn
  • X
  • Email

One of the owners of North Norfolk’s Walsingham Estate placed the first stone in the wall of Scira’s operational base at a small ceremony to mark a key stage in the building’s construction.

The laying of the stone by Elizabeth Meath Baker was carried out on Tuesday 19th June 2012 at the construction site, in Egmere, three miles south of Wells-next-the-Sea. Together with her husband Clovis, Mrs Meath Baker owns the estate, which will be home to the Scira Offshore Energy team from early next year.

The base has taken shape rapidly since its construction began in March and the ceremony marked the milestone of the erection of the steel frame.

The facility is on schedule be completed by the end of the year and is being constructed by Swaffham-based Mansell Construction Services, who are using local subcontractors and suppliers within a 30 mile radius.

Regional Managing Director of Mansell , Dean Burgess presented a specially engraved ceremonial trowel to Scira which will ultimately be displayed in a cabinet in the Operations and Maintenance base, stating “Mansell are committed to providing sustainable solutions on time to meet our customers’ requirements. We are delighted to be working with Scira Offshore Energy Limited utilizing renewable energy sources using low to zero technologies as part of the design and construction of the new Operations and Maintenance Centre.”

Scira’s General Manager Einar Strømsvåg said, “It’s exciting to see the development of our purpose built Operations and Maintenance base, as this reflects Scira’s evolution into a local company which will be part of the local community for many years to come. Moreover the permanent operations base will provide opportunities for us to develop our schools engagement programme, as we now have a home venue for educational events to support our strategy to develop skills in the local labour market.”

Sheringham Shoal Offshore Wind Farm is nearing its final stage of construction with completion scheduled for late summer 2012. The project is owned equally by Statoil and Statkraft through joint venture company Scira with Statoil the project manager during construction.

[mappress]

Offshore WIND staff, June 22, 2012; Image: Scira

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & Maintenance

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ørsted and Nuveen Inaugurate 913 MW Offshore Wind Farm in Germany
  2. 2Stillstrom Signs Semco Maritime to Build Offshore Charging Equipment
  3. 3SLPE Secures Foundation Engineering Work on EnBW’s 1 GW Dreekant Offshore Wind Farm
  4. 4DeepOcean and TFKable Plan JV for Inter-Array Cable Projects with Dedicated Vessel

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free