offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Germany: TenneT Gets Approval for Nordergründe Connection
Authorities

July 9, 2012 · about 14 years ago

Germany: TenneT Gets Approval for Nordergründe Connection

Since the update of the Energy Act in August 2009, an approval of high-voltage cables for connection of offshore wind farms is required for the implementation of planning procedures. In early 2011, TenneT filed extensive application forms for both the sea and the land route of the Nordergründe grid

2 minutes read
  • LinkedIn
  • X
  • Email

Since the update of the Energy Act in August 2009, an approval of high-voltage cables for connection of offshore wind farms is required for the implementation of planning procedures. In early 2011, TenneT filed extensive application forms for both the sea and the land route of the Nordergründe grid connection project to the authority of Lower Saxony State, which is in charge of roads and transportation (subways).

A planning process provides for full participation of the public, landowners and land users, cable operators as well as counties and municipalities. The comments and objections received regarding the land route of the network connection Nordergründe were discussed at a public hearing with the parties and the arguments from both sides were considered. Thus the network connection from the substation project Nordergründe Inhausen at sea is approved.

The decision includes the management of offshore wind park landing point of sea route at Hooksiel Inhausen to the transformer station.

The approval is given by the Lower Saxony State Agency for Road and Transport (subways) after prior notice to the participating cities and towns in the procedure designed to be available for public consultation.

Thus the initial work begins on schedule in August 2012. The owners and tenants are informed on time about both the early preparatory work, such as surveying, as well as the actual construction work later on.

The Nordergründe offshore wind farm is to be connected by a single-phase AC technology due to its proximity to the coast and because of the relatively low power of 111 MW. The 32-kilometer route will be leading from the grid connection point, the substation Inhausen, four kilometres through the coast by land and another 28 kilometers under water to the wind farm.

[mappress]

Offshore WIND staff, July 9, 2012; Image: EnergieKontor

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

AuthoritiesGrid Connection

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1DWT Returns to Riffgat Offshore Wind Farm
  2. 2Formosa 6 Offshore Wind Farm and Star Trade Enter Corporate Power Purchase Agreement
  3. 3TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  4. 4Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free