Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Vos Prodect Completes Export Cable Hang-Off Test
Grid Connection

January 22, 2014 · about 12 years ago

Vos Prodect Completes Export Cable Hang-Off Test

Vos Prodect Innovations has announced the completion of a new test on the permanent section of the cable hang-off system. With the latest test, the company’s main aim was to determine the maximum axial cable load that the permanent hang-off part can withstand. Vos Prodect has used a 3x630mm² submari

1 minutes read
  • LinkedIn
  • X
  • Email

Vos Prodect Innovations has announced the completion of a new test on the permanent section of the cable hang-off system.

With the latest test, the company’s main aim was to determine the maximum axial cable load that the permanent hang-off part can withstand.

Vos Prodect has used a 3x630mm² submarine cable, which was secured at the permanent hang-off by means of clamping on the armour wires. A pulling force up to 200kN was reached, without any sliding of the cable armour wires. Since the chinese finger used for pulling on the cable was not able to withstand greater pulling forces, the test had to be stopped.

Although the maximum load could not be determined by this test, the results are very satisfying as 200kN leaves enough safety margin in order to cope with the export cables, used for the offshore wind farms. “This means we can now take another step closer to bringing the export cable hang-off to our valued customers.”

Being an independant designer and developer of inter-array cable hang-off systems, Vos Prodect has maintained its market leading position by achieving a delivery volume of more than 900 systems over the last 2 years.

Press release, January 22, 2014; Image: Vos Prodect

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionR&DTechnology

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Subsea Battery System for Offshore Wind Completes Test Before Deployment
  2. 2EMEC Secures Multi-Million Funding for DeepWind Floating Wind Test Site
  3. 3New Study Identifies Foundation Standardisation, Lower Cost of Capital as Key to Floating Wind Competitiveness
  4. 4Subsea Micropiles to Work on Anchor Design for Pentland Floating Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free