Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›ABB, Prysmian to Supply Horns Rev 3 with Cables
Business & Finance

April 1, 2014 · about 12 years ago

ABB, Prysmian to Supply Horns Rev 3 with Cables

Energinet.dk has signed contracts with ABB and Prysmian for the supply of 220kV high-voltage cables to transport power from the Horns Rev3 offshore wind farm in the North Sea into the Danish electricity grid. ABB will supply the33 km long submarine cable for the connection of the wind turbines to th

1 minutes read
  • LinkedIn
  • X
  • Email

Energinet.dk has signed contracts with ABB and Prysmian for the supply of 220kV high-voltage cables to transport power from the Horns Rev3 offshore wind farm in the North Sea into the Danish electricity grid .

ABB will supply the33 km long submarine cable for the connection of the wind turbines to the coast at Blåbjerg , while Prysmian will provide onshore cables .

The onshore cable connection , which will bring offshore wind power to Energinet.dk’s substation in Endrup, east of Esbjerg, will be either 50 or 60 km in length , depending on the route Nature Agency suggests in the EIA process .

“Until the end of the year, we expect to grant contracts for other major wind farm components, such as transformers and a large platform to be installed at the offshore wind farm, where it will collect power from the turbines,” said Søren Juul Larsen, Project Manager from Energinet.dk .

The contract for submarine cable is worth DKK 215 million (approx. EUR 28.80 million) and it includes transport and cable-laying. The contract for onshore cable is worth DKK 82 million (approx. EUR 11 million) and it does not include the cable-burial .

(EUR 1=DKK 7.4657400)

Offshore WIND Staff, April 1, 2014; Image: ABB

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceGrid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free