The installation work on HelWin beta jacket is nearing completion, after all six piles had been driven into the seabed.

UPDATE: Installation of HelWin Beta Jacket Almost Done

Heerema Fabrication Group (HFG) said that the levelling of the piles and welding them to the jacket is about to start soon.

UPDATE: Installation of HelWin Beta Jacket Almost Done
Click to enlarge

The 4,500-tonne jacket took its position last week.

HFG’s fabrication facility Heerema Zwijndrecht is working on the final construction phase of the HelWin beta topside, due for completion in the summer of 2014.

The HelWin beta platform is being built for electricity grid operator TenneT. The platform has been developed jointly by Heerema Fabrication Group and Siemens, the main contractor for the HelWin2 project.