Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›A2SEA Wraps Up West of Duddon Sands Turbine Installation
Wind Farm Update

June 5, 2014 · about 12 years ago

A2SEA Wraps Up West of Duddon Sands Turbine Installation

SEA INSTALLER completed installation of the 108 WTGs at the West of Duddon Sands Offshore Wind Farm. In addition to the 108 WTGs, SEA INSTALLER installed 30 foundations (MPs and TPs) prior to the WTG installation. The first turbine was installed 27 September 2013, and after a rough and windy winter

1 minutes read
  • LinkedIn
  • X
  • Email

SEA INSTALLER completed installation of the 108 WTGs at the West of Duddon Sands Offshore Wind Farm. In addition to the 108 WTGs, SEA INSTALLER installed 30 foundations (MPs and TPs) prior to the WTG installation.

The first turbine was installed 27 September 2013, and after a rough and windy winter at sea, the vessel installed 44 WTGs within the last 63 days alone – including transit and load-out in Belfast.

“This is an outstanding performance by the crew on board SEA INSTALLER, the project team and our colleagues at Siemens Wind Power. It is a true example of our Team-Built culture at A2SEA,” says CEO Jens Frederik Hansen.

SEA INSTALLER will now be heading for Frederikshavn, Denmark, where she will mobilise for the Borkum Riffgrund 1 project, which counts 77 Siemens 4.0MW turbines.

The West of Duddon Sands Offshore Wind Farm is located in the East Irish Sea approximately 14 km from the nearest coast on Walney Island, Cumbria. It is a 50/50 joint venture between DONG Energy and ScottishPower Renewables and the offshore wind farm is expected to be fully operational by the end of 2014.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays
  2. 2Dogger Bank B Wind Turbine Installation Passes Halfway Mark
  3. 3GWEC Calls for Government Action to Accelerate Floating Wind Commercialisation
  4. 4France Energies Marines Launches Four Offshore Wind R&D Projects

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free