Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Ballast Nedam to Install Amrumbank West Monopiles
Wind Farm Update

August 5, 2014 · about 12 years ago

Ballast Nedam to Install Amrumbank West Monopiles

Ballast Nedam has signed a contract for the installation of monopiles at the German Amrumbank West offshore wind farm with E.ON. Ballast Nedam will erect monopiles and provide the logistics between the feeder port in Cuxhaven and the Amrumbank West offshore wind farm. The E.ON Amrumbank West offshor

1 minutes read
  • LinkedIn
  • X
  • Email

Ballast Nedam has signed a contract for the installation of monopiles at the German Amrumbank West offshore wind farm with E.ON.

Ballast Nedam will erect monopiles and provide the logistics between the feeder port in Cuxhaven and the Amrumbank West offshore wind farm.

The E.ON Amrumbank West offshore wind farm is a 288 MW offshore wind farm in the North Sea, Germany. It is located 35 km north of Helgoland and 37 km west of Amrum.

For installing the monopiles with diameters of 6m, heights up to 70m and weights up to 800 ton, Ballast Nedam will use its Heavy Lift Vessel (HLV) Svanen. Installation strategy is based on the feeder concept bringing monopiles floating to the HLV Svanen at the installation site. This method has been optimized over recent years resulting in highly efficient installation cycles. To date, HLV Svanen has successfully installed over 500 offshore wind turbine foundations.

HLV Svanen has arrived in Cuxhaven and the installation works for the vessel are planned to start mid August this year.

The project fits perfectly in the strategy of Ballast Nedam which is aimed to deliver cost efficient foundation solutions to the offshore wind industry. By optimizing logistic and installation solutions, Ballast Nedam is supporting the general development of offshore wind in Europe.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free