offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Dialogue Paper on Kriegers Flak Delayed
Authorities

December 2, 2014 · about 11 years ago

Dialogue Paper on Kriegers Flak Delayed

The publishing of the dialogue paper on Danish offshore wind farm Kriegers Flak is slightly delayed, the Danish Energy Agency (DEA) notified on its website. “We expect the paper to be published next week,” the DEA said. In order to ensure that potential tenderers can offer their views on these frame

1 minutes read
  • LinkedIn
  • X
  • Email

The publishing of the dialogue paper on Danish offshore wind farm Kriegers Flak is slightly delayed, the Danish Energy Agency (DEA) notified on its website.

“We expect the paper to be published next week,” the DEA said.

In order to ensure that potential tenderers can offer their views on these framework conditions and contribute to making the contents of these conditions attractive and flexible for the market, the Danish Energy Agency decided to conduct a technical dialogue in May 2013 covering the two projects Horns Rev 3 and Kriegers Flak.

While the tender for Horns Rev 3 has proceeded as planned, there have been important changes to the Kriegers Flak project following the first and successful market dialogue.

Considering the magnitude of the changes the Danish Energy Agency has decided to renew the call for a technical dialogue concerning Kriegers Flak. The aim is still to make the tendering procedure and conditions as attractive and flexible as possible.

The form of the dialogue will be through the Danish Energy Agency asking the market specific questions on the basis of selected themes in this dialogue paper. Potential tenderers will be able to detail their written replies and views in bilateral meetings with the Danish Energy Agency. The replies will help drafting of the preliminary tender conditions.

[mappress mapid=”14915″]

Source: Danish Energy Agency

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

AuthoritiesR&DWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1DWT Returns to Riffgat Offshore Wind Farm
  2. 2Formosa 6 Offshore Wind Farm and Star Trade Enter Corporate Power Purchase Agreement
  3. 3TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  4. 4Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free