Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›First Power at Eneco Luchterduinen
Operations & Maintenance

May 25, 2015 · about 11 years ago

First Power at Eneco Luchterduinen

Last Friday saw a completion of the 240-hour test phase of the first of 43 wind turbines at offshore wind park Eneco Luchterduinen. This means that the wind park is now generating green energy for the Dutch grid. According to Van Oord, the installation of the wind turbines is progressing well with o

1 minutes read
  • LinkedIn
  • X
  • Email

Last Friday saw a completion of the 240-hour test phase of the first of 43 wind turbines at offshore wind park Eneco Luchterduinen.

This means that the wind park is now generating green energy for the Dutch grid.

According to Van Oord, the installation of the wind turbines is progressing well with offshore installation vessel Aeolus setting up the 31st wind turbine.

Every turbine consists of five sections: a tower with a diameter of 4.5 m, the gondola weighing 165 tonnes and three rotor blades with a 112 m diameter. The vessel can carry all sections and components for eight complete turbines in one go. The Aeolus is currently working on the fourth load.

The electricity comes ashore near Noordwijk via a 25 km cable buried in the sea bed and continues underground for a further eight km to the Tennet high-tension power station in Sassenheim. Depending on the weather, the wind park can be fully operational in August 2015.

Together with the Mitsubishi Corporation, energy company Eneco is developing wind park Eneco Luchterduinen 23 km off the coast of Noordwijk and Zandvoort. The 43 wind turbines will generate green energy for almost 150,000 households.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & Maintenance

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Njord Survey Inks Three-Year Agreement with RWE
  2. 2Jan De Nul Orders Another Newbuild Trenching Support Vessel
  3. 3DEHN Launches Digital Platform for Wind Turbine Lightning Monitoring
  4. 4Cadeler and Vattenfall to Explore Next-Gen Offshore Wind Major Component Exchange Solutions

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free