Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›R&D›NORCOWE Installs First Equipment at FINO 1
R&D

May 25, 2015 · about 11 years ago

NORCOWE Installs First Equipment at FINO 1

Scientists from CMR have successfully completed the first installation phase for the measurement campaign at the FINO1 research platform. The campaign is carried out by CMR and UIB in close cooperation with the other NORCOWE partners, FuE-Zentrum FH Kiel, Fraunhofer IWES, RAVE and ForWind. Two Windc

1 minutes read
  • LinkedIn
  • X
  • Email

Scientists from CMR have successfully completed the first installation phase for the measurement campaign at the FINO1 research platform.

The campaign is carried out by CMR and UIB in close cooperation with the other NORCOWE partners, FuE-Zentrum FH Kiel, Fraunhofer IWES, RAVE and ForWind.

Two Windcube 100s scanning wind lidars from LeoSphere and a RPG HATPRO microwave temperature profiler are now operational and connected to the FINO1 network, providing online data access, remote monitoring and control of the instruments.

Deployment of the oceanographic instrumentation is planned for the first week of June with the research vessel Håkon Mosby from IMR. In the same timeframe, the researchers will proceed with the second installation phase at FINO1 for the DCF sonic turbulence meters and breaking wave camera system.

The meteorological and oceanographic measurements will run in parallel until the fall, when the oceanographic measurement buoys will be recovered. The meteorological measurements at FINO1 will continue until June 2016.

Image: Norcowe

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

R&DTechnology

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  2. 2Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  3. 3All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  4. 4Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free