JDR Wins Cabling Job at Rampion OWF

Wind Farm Update

JDR has been awarded a contract by E.ON, alongside partners the UK Green Investment Bank plc (GIB), to supply its subsea cabling technology and services for the Rampion Offshore Wind Farm.

The contract, which commenced in May 2015 and is expected to last for 17 months, will see JDR design and manufacture 142 kilometers of 36 kilovolt inter-array cables for the project.

The scope of work also includes the supply of hang-offs, electrical t-connectors, inner cone connectors, cable cleats and a J-tubeless cable protection system specifically designed to optimise installation time and minimise the potential for cable damage during installation and operation.

JDR will pre-commission the entire cabling system from its industry-leading manufacturing facility in Hartlepool.

Image: JDR