Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›SgurrEnergy Advises Borkum Project Lenders
News

September 10, 2015 · about 11 years ago

SgurrEnergy Advises Borkum Project Lenders

SgurrEnergy has acted as technical advisor on behalf of the 200MW Borkum wind farm lenders during the financing and construction monitoring phases of the project. The project was officially opened by the developer, Trianel GmbH, at a ceremony held on 31 August 2015. The project, located approximatel

2 minutes read
  • LinkedIn
  • X
  • Email

SgurrEnergy has acted as technical advisor on behalf of the 200MW Borkum wind farm lenders during the financing and construction monitoring phases of the project.

The project was officially opened by the developer, Trianel GmbH, at a ceremony held on 31 August 2015.

The project, located approximately 45 km to the north of the East Friesian German island of Borkum, consists of 40 wind turbines and will have the capacity to supply the electricity of approximately 200,000 households. Borkum is the first municipally owned offshore wind farm in Europe and, together with Global Tech I wind farm, on which SgurrEnergy also acted as lenders’ technical advisor, Borkum is one of the first commercial projects to use tripod foundations.

The SgurrEnergy team began working on the project in 2009 and has been carrying out construction monitoring activities since the summer of 2011. The company’s technical advisor scope included monthly reporting to the project lenders on construction progress, programme and budget reviews, as well as on-site monitoring of progress through site visits. SgurrEnergy, a Wood Group company, will continue to advise the lenders throughout the early stages of operation as it moves into the next phase of operations monitoring.

SgurrEnergy’s Andrew Cole, Associate Director within the Advisory Services Group , said: “Having been involved with Borkum since the beginning of the financing process in 2009, and working through a challenging and ground-breaking construction phase, it’s great to see the project now successfully into operation.

We would like to congratulate all of the team at Trianel GmbH on achieving this significant milestone and we look forward to working with them as the project moves into the next exciting phase.”

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Offshore Charging, Rare Earth Magnet Projects Secure EU Funding
  2. 2Terna Energy Plans 45 MW Floating Wind Pilot in Greece
  3. 3Kumagai Gumi Joins DemoSATH as Floating Wind Test Project Extended Through 2027
  4. 4New Zealand Opens First Offshore Wind Feasibility Permit Round

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free