offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Energinet.dk Orders €33.5M Worth of Components for Kriegers Flak Connection
Grid Connection

January 15, 2016 · about 10 years ago

Energinet.dk Orders €33.5M Worth of Components for Kriegers Flak Connection

Energinet.dk has awarded DKK 250 million (approx. EUR 33.5 million) in contracts for the supply of technical components for Kriegers Flak grid connection. The components include transformers, reactors and switchgear for power stations that will connect the offshore wind farm with the Danish grid. Th

1 minutes read
  • LinkedIn
  • X
  • Email

Energinet.dk has awarded DKK 250 million (approx. EUR 33.5 million) in contracts for the supply of technical components for Kriegers Flak grid connection.

The components include transformers, reactors and switchgear for power stations that will connect the offshore wind farm with the Danish grid.

The Danish transmission company said this is the biggest purchase of AC components for power stations in its history. Total budget for Kriegers Flak grid connection is DKK 3.5 billion (approx. EUR 469 million).

The purchase of components is divided into seven contracts, some of which have been concluded as framework agreements.

CG will deliver power transformers and Gas Insulated Switchgear (GIS), ABB and Siemens are in charge of providing reactors, and Royal SMIT will provide a phase shifter transformer.

“With the placement of orders we have ensured timely deliveries, which means that we are ready to plug in Denmark’s largest offshore wind farm on time in 2018,” said Energinet.dk’s chief project manager Jens Christian Hygebjerg .

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionTechnologyWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1DWT Returns to Riffgat Offshore Wind Farm
  2. 2Formosa 6 Offshore Wind Farm and Star Trade Enter Corporate Power Purchase Agreement
  3. 3TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  4. 4Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free