Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Ecosse Subsea Systems Doubles Wikinger Workload
Grid Connection

August 1, 2016 · about 10 years ago

Ecosse Subsea Systems Doubles Wikinger Workload

Ecosse Subsea Systems (ESS) has extended a trenching scope on the 350MW Wikinger offshore wind farm in the Baltic Sea with the award of a seabed clearance project. The Scottish company was last year awarded a contract by main contractor Prysmian Group to carry out pre-cut seabed trenching, prior to

1 minutes read
  • LinkedIn
  • X
  • Email

Ecosse Subsea Systems (ESS) has extended a trenching scope on the 350MW Wikinger offshore wind farm in the Baltic Sea with the award of a seabed clearance project.

The Scottish company was last year awarded a contract by main contractor Prysmian Group to carry out pre-cut seabed trenching, prior to cable laying, on Iberdrola’s 70-turbine wind farm offshore Germany.

The initial contract has now doubled in scope with the award of route clearance and seabed preparation work on the Wikinger development.

“Detailed surveys discovered a number of obstacles on the proposed route and we have been contracted by Prysmian Group to carry out seabed clearance and route preparation prior to commencing the trenching work,” Keith McDermott, ESS commercial director, said.

“This is an area in which we have a great deal of experience and strong track record of working in different terrains and our SCAR Route Clearance system has been used in similar projects in the Baltic Sea.”

Once the seabed is prepared, ESS’s SCAR Seabed System will perform first pass and multi-pass trenching in preparation for Prysmian’s installation and burial of 81km of submarine cables which will connect the turbines to the offshore substation.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionTechnologyVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free