Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›Semco Maritime to Build, Install Seajacks Scylla’s Sea Fastening Kit
Vessels

September 21, 2016 · about 10 years ago

Semco Maritime to Build, Install Seajacks Scylla’s Sea Fastening Kit

Semco Maritime has won a contract to fabricate and install a sea fastening system on Seajacks Scylla, the world’s largest wind turbine installation vessel. Semco Maritime is to construct a special module, which will render it possible to adapt Seajacks Scylla’s freight deck to accommodate different

1 minutes read
  • LinkedIn
  • X
  • Email

Semco Maritime has won a contract to fabricate and install a sea fastening system on Seajacks Scylla, the world’s largest wind turbine installation vessel.

Semco Maritime is to construct a special module, which will render it possible to adapt Seajacks Scylla’s freight deck to accommodate different sizes of towers and blades.

Seajacks has designed the fastening solution, which is to be constructed on land and mounted on the vessel when she arrives in Esbjerg, Denmark, in November 2016, said Lars Skov, Head of Rig Projects at Semco Maritime.

”Rig Projects will handle project management while our own fabrication department will support with the fabrication at our yard in Esbjerg making this a truly tailor-made task for Semco Maritime,” said Skov.

”We only have ”Scylla” in Esbjerg for 18 days, and during that period we are to mount a complex prefabricated solution. That is obviously a very sharp deadline, which we are only able to live up to because of our year-long experience with management of urgent rig projects in combination with our dockyard expertise from this exact type of module construction.”

Semco Maritime expects to complete all the works on Seajacks Scylla by 18 December.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Vessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Wood Thilsted Secures New Contract on Outer Dowsing Offshore Wind Farm
  2. 2Vattenfall to Offer 200 MW of Balancing Power from German Offshore Wind Farm
  3. 3Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  4. 4Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free