ZTT Delivers Binhai North Offshore Wind Farm Cables

Grid Connection

Chinese cable maker ZTT Group has delivered a 220kV submarine composite cable for the 400MW Binhai North Phase 2 offshore wind farm in the Jiangsu province.

Source: ZTT/Twitter

Back in November 2016, China Power Complete Equipment Co. (CPCEC) accepted ZTT Group’s CNY 298 million (EUR 40.8 million) bid to provide 35kV and 220kV cables and accessories for the wind farm.

The cables and the accessories are manufactured in ZTT’s submarine cable factory in Jiangsu.

The Binhai North Phase 2 is being developed by the State Power Investment Corporation (SPIC). The wind farm comprises 100 4MW wind turbines and a 400MW substation which will be installed some 22 kilometres off the coast.

Back in May 2016, Danish engineering, design and consultancy company Ramboll won a contract to design the wind farm.