DeepOcean to Link Merkur Offshore Wind Farm to DolWin Gamma

Grid Connection

DeepOcean has been awarded a contract by Norddeutsche Seekabelwerke GmbH (NSW) for export cable transportation, installation and trenching services on the 396MW Merkur offshore wind farm in the German Bight.

Image source: DeepOcean

The 66-turbine Merkur offshore wind farm is located 45km north of the island Borkum in the North Sea, within the exclusive economic zone of Germany.

NSW is contracted by TenneT Offshore GmbH (TOG) to establish the grid connection between the Merkur offshore substation and the DolWin gamma converter platform. The designated export cable connection will comprise two parallel 150kV rated HVAC cables.

One of the specific technical challenges of the Merkur grid connection is the fact that the export cable corridor crosses nine live cables and one commissioned offshore wind farm, DeepOcean said.

DeepOcean is contracted by NSW for the marine works associated with the transportation, installation and burial of the HVAC cables from the DolWin gamma converter platform towards the Merkur offshore substation.

In addition to the transportation, installation and trenching of the two parallel export cables, the work scope includes a burial assessment study, route surveys, route engineering, pre-lay grapnel runs, installation of cable protection systems and pre/post-lay crossing protection works.

The work is scheduled to be executed in 2018 by DeepOcean’s in-house fleet of dedicated offshore installation and trenching vessels.