Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›All Nissum Turbines Installed, Cabling Work Nearing Completion
Grid Connection

February 8, 2018 · about 8 years ago

All Nissum Turbines Installed, Cabling Work Nearing Completion

The fourth and final Siemens Gamesa 7MW wind turbine was installed at the Nissum Bredning site in January, with cabling works now well underway and expected to be completed soon, according to the project’s social media page.

1 minutes read
  • LinkedIn
  • X
  • Email

The fourth and final Siemens Gamesa 7MW wind turbine was installed at the Nissum Bredning site in January, with cabling works now well underway and expected to be completed soon, according to the project’s social media page.

The installation of cable pipes started in late December 2017 and was completed in the second half of January 2018, when JD-Contractor and Swiss company Plumettaz started laying the cables through the pipes as part of the novel “Cable in pipe” concept that is being tested at the Danish offshore wind test site.

Nissum Bredning wind farm was expected to produce first power last month, however, the challenging weather conditions have been disrupting the works and currently the project team is working on laying the two last cables through the pre-installed pipes. With the first days of February, JD-Contractor and Jysk Energy, which connects the cables on land, linked the export cable from wind turbine position M2 to the transformer station in Thyborøn.

Once completed, the 28MW offshore wind farm, which serves as a testbed for Siemens’ technology, will get support by receiving a guaranteed feed-in tariff of DKK 0.7/kWh (EUR 0.09/kWh) for the initial 10 years for the first 50,000 full load hours of operation.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free