Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›Stanislav Yudin In Charge of Beatrice Jacket Installation
Vessels

April 3, 2018 · about 8 years ago

Stanislav Yudin In Charge of Beatrice Jacket Installation

Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has been deployed on the jacket installation at the Beatrice offshore wind farm as the heavy lift vessel Oleg Strashnov left the site to handle the substation installation at the Arkona offshore wind farm in the German part of the Baltic Sea.

1 minutes read
  • LinkedIn
  • X
  • Email

Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has been deployed on the jacket installation at the Beatrice offshore wind farm as the heavy lift vessel Oleg Strashnov left the site to handle the substation installation at the Arkona offshore wind farm in the German part of the Baltic Sea.

Oleg Strashnov’s AIS data from 3 April show that the vessel is already at the Arkona offshore construction site and, according to Notice to Mariners for the Beatrice project, Stanislav Yudin is now leading the jacket installation.

Forty-five foundations out of the total of 86 have been already installed at the Beatrice site, which will house 84 Siemens Gamesa 7MW wind turbines and two Offshore Transformer Modules (OTMs), all supported by jackets.

In January, Oleg Strashnov left the Beatrice wind farm to install the offshore substation at the Merkur offshore wind farm , and returned to the jacket installation at the UK offshore wind farm right after completing the works at the German Merkur project.

The Beatrice project site is currently accommodating several activities, including jacket installation, inter-array cable installation, export cable installation, and the commissioning of the first of its two OTMs.

The first wind turbine at the 588MW offshore wind farm is scheduled to be installed this summer and the project is expected to be operational by the end of 2019.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

VesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free