Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›EDS Completes Aberdeen Bay Work
Grid Connection

October 12, 2018 · about 8 years ago

EDS Completes Aberdeen Bay Work

EDS HV Group has completed its scope of work at Vattenfall’s European Offshore Wind Deployment Centre (EOWDC), also known as the Aberdeen offshore wind farm.

2 minutes read
  • LinkedIn
  • X
  • Email

EDS HV Group has completed its scope of work at Vattenfall’s European Offshore Wind Deployment Centre (EOWDC), also known as the Aberdeen offshore wind farm.

EDS, part of James Fisher and Sons, was sub-contracted by Boskalis for the cable termination and testing work.

Located off Aberdeen Bay, the 93.2MW offshore wind farm has 11 wind turbines, including the two of the most powerful units ever installed – the MHI Vestas 8.8MW turbines.

The EOWDC project has enabled Swedish energy group Vattenfall, the developers behind the wind farm, to trial new technology and is only the second commercial offshore wind farm worldwide to use a 66kV cabling system. Compared with conventional 33kV cabling less inter-array cabling is required, and this reduces construction costs, EDS said.

EDS completed the cable termination and testing work on the 11 assets.

In addition, EDS HV Management also provided HV consulting services to the EOWDC as part of a separate contract that included safety rules implementation, the supply of Senior Authorised Persons (SAPs), network and SCADA system review and commissioning support services.

Ken Ritson , Group Managing Director of EDS, said: “66kV is quickly becoming the industry norm, and any change such as this needs to be carefully managed. EDS were happy to offer the enhanced level of competence and experience required to help to manage this change.”

Overall, the EOWDC involved just over 21km of cabling from the offshore site to the substation in Blackdog, Aberdeenshire – similar to the distance from Aberdeen to Stonehaven.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionJobs & RecruitmentWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free