Beatrice All About Number Seven

Wind Farm Update

Swire Blue Ocean’s jack-up Pacific Orca installed 77 out of 84 Siemens Gamesa 7MW wind turbines on the Beatrice wind farm offshore Scotland as of 29 April, with seven more turbines left to be installed.

BOWL

73 of the turbines installed in the Outer Moray Firth were commissioned, Beatrice Offshore Windfarm Limited (BOWL), owner and developer of the 588MW wind farm, said.

Pacific Orca is loading the turbines in sets of five at the Nigg port, Siemens Gamesa’s pre-assembly base, and installing them at the site 13 kilometres off the Caithness coast.

The commissioning works are carried out using a combination of the walk-to-work vessel Island Crown and crew transfer vessels Fob Swath 3 and Seacat Resolute. The wind farm is expected to be completed this Spring.

BOWL is a joint venture partnership between SSE (40%), Copenhagen Infrastructure Partners (35%) and Red Rock Power Limited (25%).