ProCon Wraps Up Borssele 1&2 TP Work

ProCon Wraps Up Borssele 1&2 TP Work

Wind Farm Update

ProCon Wind Energy has completed the electrical construction of 35 transition pieces for the Borssele 1 & 2 offshore wind project at EEW Offshore Structures (Britain) Ltd.

ProCon stated that all its tasks have been finished and now only an O&M manual remains for total completion.

EEW OSB

The company has been providing electrical pre-assembly, installation and connection of 35 E-modules and platforms, as well as installation of different systems, including external lighting, navigation, communication and ventilation, since June 2019.

In addition, ProCon carried out commissioning and testing of the electrical construction of each transition piece.

The Borssele 1&2 offshore wind farm will comprise 94 Siemens Gamesa 8MW turbines installed some 23km off the Dutch coast.

EEW OSB loaded out the final transition pieces built for the wind farm at the beginning of January. Denmark’s Bladt Industries is in charge of manufacturing and delivering the remaining 59 transition pieces.

While the final documentation detail for Borssele 1 & 2 is added, ProCon and EEW began working on the 30 transition pieces for the Hornsea Two offshore wind project.