Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Scaldis Getting Ready to Install Second SeaMade Substation
Grid Connection

March 13, 2020 · about 6 years ago

Scaldis Getting Ready to Install Second SeaMade Substation

Scaldis Salvage & Marine Contractors is currently preparing for the installation of the second offshore substation at the SeaMade wind farm in Belgium. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. This second topside, which recently

1 minutes read
  • LinkedIn
  • X
  • Email
Scaldis Getting Ready to Install Second SeaMade Substation
Scaldis

Scaldis Salvage & Marine Contractors is currently preparing for the installation of the second offshore substation at the SeaMade wind farm in Belgium.

The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects.

This second topside, which recently arrived in Vlissingen, the Netherlands, will be installed at the Seastar concession by heavy lift vessel Gulliver.

The first offshore substation was installed at the project site in the Belgian North Sea earlier this month.

The two substations will collect the electricity produced by 58 Siemens Gamesa 8.4MW turbines, convert it from 33kV to 220kV, and export it into the grid via Elia’s Modular Offshore Grid .

DEME Offshore, Engie, Tractebel and Smulders are responsible for the full engineering, procurement, construction, transport, installation, and commissioning of the substations.

Full wind farm commissioning is expected by the end of the year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1200th Vestas V236-15.0 MW Wind Turbine Installed Offshore
  2. 2Neptun Werft-Smulders Joint Venture Secures Second 2 GW Converter Platform Contract from 50Hertz
  3. 3First Data from ‘Most Ecological Offshore Wind Farm’ Made Publicly Available
  4. 4EEW SPC to Supply TP-Less Monopiles for First Phase of CIP and Vattenfall’s Zeevonk Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free