Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Technology›Kaskasi Monopiles to Be Hammered In with CAPE Holland’s Vibro Tool
Technology

April 8, 2020 · about 6 years ago

Kaskasi Monopiles to Be Hammered In with CAPE Holland’s Vibro Tool

Seaway 7 has signed a contract with CAPE Holland for the supply of Vibro Lifting Tool (VLT) for the installation of monopile foundations at the Kaskasi offshore wind farm.

2 minutes read
  • LinkedIn
  • X
  • Email
Seaway 7 has signed a contract with CAPE Holland for the supply of Vibro Lifting Tool (VLT) for the installation of monopile foundations at the Kaskasi offshore wind farm.
Illustration; CAPE Holland/Vibro driving at Riffgat offshore wind farm

Seaway 7 has signed a contract with CAPE Holland for the supply of Vibro Lifting Tool (VLT) for the installation of monopile foundations at the Kaskasi offshore wind farm.

According to CAPE Holland, this will be the first offshore wind project whose monopiles will be driven to final penetration with a vibro hammer only.

For the Kaskasi project, multiple vibro hammers will be linked together to provide a total of 1,920 kilogram-metres and a specially developed clamping system will be used to create an interface between the Vibro Lifting Tool and the flanged top of the monopiles.

“We have always believed to be able to provide an installation tool which can significantly reduce overall costs of the installation of monopiles for offshore wind farms and we’re very happy that all our hard work over the previous years is now paying off and creating the opportunity for us to prove this” , said Laurens de Neef , CAPE Holland CEO.

Seaway 7 will carry out the transport and installation of the offshore substation foundation, 38 wind turbine monopile foundations and inner array grid cables under a contract between innogy and Subsea 7, Seaway 7’s parent company.

The foundation installation work will start in the third quarter of 2021.

Seaway 7 already used CAPE Holland’s vibro equipment on multiple projects. In 2012, the vibro hammer was deployed for the first time to drive the monopiles to a stable depth at the Riffgat offshore wind farm site. Last year, the offshore construction company also used the vibro tool on an offshore wind project in Taiwan, CAPE Holland said.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Technology

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free