offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Hollandse Kust Zuid Export Cables Set Sail from Greece to Netherlands
Grid Connection

July 7, 2020 · about 6 years ago

Hollandse Kust Zuid Export Cables Set Sail from Greece to Netherlands

The export cables for TenneT’s Hollandse Kust Zuid grid connection have been sent off from Greece to the Netherlands, according to the Dutch cable logistics company WIND, which handled the load-out. The company has been hired by Van Oord to provide subsea cable logistics for the grid connection proj

2 minutes read
  • LinkedIn
  • X
  • Email
Load-out of the Hollanse Kust Zuid export cable onto a barge with cable carousels on board
WIND

The export cables for TenneT’s Hollandse Kust Zuid grid connection have been sent off from Greece to the Netherlands, according to the Dutch cable logistics company WIND, which handled the load-out.

The company has been hired by Van Oord to provide subsea cable logistics for the grid connection project, for which Van Oord has been contracted by TenneT and is delivering export cables manufactured by the Greek cable supplier Hellenic Cables.

WIND is also responsible for two separate load-outs from the transport vessel to Van Oord’s cable laying vessel Nexus and one load-out into the storage.

TenneT awarded a contract for the connection of the Hollandse Kust Zuid (HKZ) Alpha and Beta offshore platforms to the Dutch onshore grid to a consortium between Van Oord and Hellenic Cables in 2018.

The scope of work for the 700 MW Alpha project covers the design, the manufacture of 220 kV cables, cable-laying operations, and connecting the wind farm to the Maasvlakte high-voltage station.

The consortium is also in charge of supplying and installing the cables for the HKZ Beta project, including manufacturing and installation of a 66 kV subsea cable between the Alpha and Beta platforms.

The Hollandse Kust Zuid Alpha grid connection will be ready by 2021, and the Beta is scheduled for completion in 2022.

The Dutch Hollandse Kust Zuid zone comprises four offshore wind farms that will be connected to the HKZ Alpha and HKZ Beta substations. The wind farms are being developed by Vattenfall.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid Connection

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  2. 2Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study
  3. 3Industrialisation, Productivity and Global Competition: What's Next for Blade Manufacturing?
  4. 4Massachusetts Invests USD 4.2 Million to Boost Offshore Wind Workforce and Research

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free