Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›Seajacks Scylla Installs First Moray East Jacket
Vessels

July 7, 2020 · about 6 years ago

Seajacks Scylla Installs First Moray East Jacket

The first jacket foundation is now in place at the Moray East offshore wind farm in Scotland. DEME Offshore, in charge of the installation works, is currently using the Seajacks Scylla jack-up vessel to install the jackets. The 950 MW offshore wind project will comprise 100 MHI Vestas 9.5 MW wind tu

2 minutes read
  • LinkedIn
  • X
  • Email
The first Moray East yellow jacket foundation installed at the offshore project site
DEME

The first jacket foundation is now in place at the Moray East offshore wind farm in Scotland. DEME Offshore, in charge of the installation works, is currently using the Seajacks Scylla jack-up vessel to install the jackets.

The 950 MW offshore wind project will comprise 100 MHI Vestas 9.5 MW wind turbines and three offshore substations, all of which will be installed on jacket foundations.

“Despite the ongoing challenges of the Coronavirus pandemic and a last-minute crane failure prior to the delivery of DEME’s newbuild offshore installation vessel ‘Orion’, DEME Offshore has achieved the installation of the first jacket in good time and got this phase of the project off to a strong start” , DEME Offshore stated in a press release on 6 July.

DEME’s installation vessel Orion , initially scheduled to be deployed for Moray East jacket installation, was replaced by Seajacks Scylla following an accident on board Orion at the beginning of May, when the vessel’s crane hook broke, leaving several people injured and damaging the vessel’s crane and deck.

A few days after the accident, DEME revealed it was looking for another vessel to fulfill its contract for the Moray East project.

The company has been contracted for the design, fabrication and installation of the 103 foundations, and the installation of three topsides for the project’s substations (Offshore Transformer Modules; OTMs).

The first of the three OTM topsides is now also on the way to be installed.

The Moray East offshore wind farm, developed by ENGIE and EDP Renewables, is scheduled to be fully operational in 2022.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

VesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Dajin Heavy Industry Adds Third Large Deck Transport Vessel to Its Fleet
  2. 2Tekmar Nets EUR 6 Million Contract Extension in Offshore Wind
  3. 3Subsea Micropiles to Invest GBP 5 Million in Expanding Manufacturing, Offshore Ops at Scottish Port
  4. 4SSE Picks Montrose Port as O&M Base for 1.4 GW Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free