Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Polish Join Hollandse Kust Noord OSS Work
Grid Connection

October 8, 2020 · about 6 years ago

Polish Join Hollandse Kust Noord OSS Work

Ultra NDT S.C. and Jaworski Energy Services have signed a contract with the ENGIE Solutions Belgium and Iemants joint venture for work on the Hollandse Kust Noord substation topside. Ultra NDT S.C. has been selected as the third-party responsible for non-destructive testing, with Jaworski Energy Ser

1 minutes read
  • LinkedIn
  • X
  • Email
Polish Join Hollandse Kust Noord OSS Work
TenneT

Ultra NDT S.C. and Jaworski Energy Services have signed a contract with the ENGIE Solutions Belgium and Iemants joint venture for work on the Hollandse Kust Noord substation topside.

Ultra NDT S.C. has been selected as the third-party responsible for non-destructive testing, with Jaworski Energy Services providing project management and technical supervision over the contracted scope.

ENGIE Fabricom and Iemants started engineering work on the Hollandse Kust Noord offshore transformer station in June, with construction work for the topside and the jacket scheduled to start this month.

The joint venture’s scope of work consists of the engineering, procurement, construction, offshore installation, connection and testing of the offshore transformer station.

The substation consists of a 45m high jacket of 1,930t and 870t piles to be placed in 24m water depth, and a topside structure consisting of four decks weighing approximately 4,100t. The topside structure is 47m long, 35m wide and 25m high.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free