Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›GE Haliade-X for First Large-Scale US Offshore Wind Farm
Wind Farm Update

December 2, 2020 · about 5 years ago

GE Haliade-X for First Large-Scale US Offshore Wind Farm

Vineyard Wind has selected GE Renewable Energy as the preferred turbine supplier for the first U.S. large-scale offshore wind project. Vineyard Wind 1 will feature the GE Haliade-X units, the most powerful offshore wind turbine in operation to date. As a part of reaching this milestone, the develope

2 minutes read
  • LinkedIn
  • X
  • Email
GE Haliade-X for First Large-Scale US Offshore Wind Farm
GE Renewable Energy

Vineyard Wind has selected GE Renewable Energy as the preferred turbine supplier for the first U.S. large-scale offshore wind project.

Vineyard Wind 1 will feature the GE Haliade-X units, the most powerful offshore wind turbine in operation to date.

As a part of reaching this milestone, the developer has also decided to temporarily withdraw its Construction and Operations Plan (COP) from further review by the U.S. Bureau of Ocean Energy Management (BOEM) to allow the project team to conduct a final technical review associated with the inclusion of Haliade-X into the final project design.

“The selection of GE as our preferred turbine supplier means that a historic American company will play a vital role in the development of the first commercial-scale offshore wind power in the U.S.,” said Vineyard Wind CEO Lars T. Pedersen .

“While the decision to pause the ongoing process was difficult, taking this step now avoids potentially more federal delays and we are convinced it will provide the shortest overall timeline for delivering the project as planned. We intend to restart the BOEM process from where we left off as soon as we complete the final review.”

Vineyard Wind expects its review to take several weeks, after which it will resume the Federal permitting process with BOEM. With buffer built into the project schedule, the company still expects to reach financial close in the second half of 2021 and to begin delivering clean energy in 2023.

Back in 2018, MHI Vestas was selected as the preferred turbine supplier for the 800 MW project. However, the deal is said to have been canceled due to the project’s permitting hold-up.

The joint venture company of Avangrid Renewables and Copenhagen Infrastructure Partners (CIP) is developing the wind farm 56km off the coast of the Massachusetts mainland.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free