Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Teras Offshore Inks EUR 69 Million Contract for Taipower Project’s Phase II
Contracts & Tenders

December 7, 2020 · about 5 years ago

Teras Offshore Inks EUR 69 Million Contract for Taipower Project’s Phase II

Teras Offshore, a wholly owned subsidiary of Ezion Holdings, has signed a deal worth USD 83.4 million (around EUR 68.7 million) for the transportation and installation of 31 9.5 MW offshore wind turbines at Taipower Offshore Wind Project Phase II (TPC Changhua Phase II). The contract was awarded by

1 minutes read
  • LinkedIn
  • X
  • Email
A Siemens Gamesa offshore wind turbine
Siemens Gamesa; Illustration

Teras Offshore, a wholly owned subsidiary of Ezion Holdings, has signed a deal worth USD 83.4 million (around EUR 68.7 million) for the transportation and installation of 31 9.5 MW offshore wind turbines at Taipower Offshore Wind Project Phase II (TPC Changhua Phase II).

The contract was awarded by Foxwell, an affiliate company of Shinfox Corp, which won the tender from Taiwan Power Company (TPC) to develop the project in June, under a contract valued at a total of TWD 62.89 (around EUR 1.8 billion).

The wind farm, located approximately 14.7 kilometres west of Lukang in Changhua County, is expected to come online by September 2025. According to information from June, the project will feature Siemens Gamesa wind turbines.

Shinfox was scheduled to start offshore surveys, including geological seabed investigations, this year. The detailed design is set to be carried out in 2021 and the following year the manufacturing of substructures, wind turbines and related equipment will begin. The installation of subsea cables, foundations and wind turbines is expected to be done in 2024 and 2025.

The TPC Changhua Phase II was one of the eleven offshore wind projects selected by the Taiwanese government in April 2018 to be developed by 2025. Taipower is currently developing the 109.2 MW TPC Changhua Phase I wind farm expected to be completed by the end of the year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & TendersWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  2. 2All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  3. 3Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind
  4. 4ScottishPower Renewables Completes ‘Record-Breaking’ Cable Landfall Operation for East Anglia Two

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free