Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›All Windpark Fryslân Array Cables In Place
Grid Connection

May 24, 2021 · about 5 years ago

All Windpark Fryslân Array Cables In Place

The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands. The inter-array cables will undergo tests in the coming days, Windpark Fryslân said. The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbi

1 minutes read
  • LinkedIn
  • X
  • Email
Windpark Fryslân
Windpark Fryslân

The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands.

The inter-array cables will undergo tests in the coming days, Windpark Fryslân said.

The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbines with the wind farm’s own transformer station at Breezanddijk on the artificial island of Breezand.

From there, two cable circuits which run to Bolsward deliver the electricity generated at the wind farm to TenneT’s Frisian high-voltage grid.

Related Articles

Wind Farm Update

First Power Flows from Windpark Fryslân

1 min read

Located some six kilometres off the Frisian coast, the 382.7 MW Windpark Fryslân is the largest wind farm built in a body of fresh water.

The wind farm is being constructed by the Zuiderzeewind consortium of Van Oord and Siemens Gamesa on behalf of Ventolines.

Turbine installation is currently ongoing and the wind farm is expected to be completed by the summer of 2021.

Ventolines is responsible for the project management of Windpark Fryslân during construction and operations.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free