offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Energinet Seeks Export Cable Provider for Thor Offshore Wind Farm
Contracts & Tenders

February 24, 2022 · about 4 years ago

Energinet Seeks Export Cable Provider for Thor Offshore Wind Farm

Danish transmission system operator Energinet has issued a contract notice for the procurement of the onshore export cable section for the 1 GW Thor offshore wind farm. The wind farm’s onshore grid connection consists of 21 individual cable sections each containing two 220 kV cable systems with a co

1 minutes read
  • LinkedIn
  • X
  • Email
An image mapping Thor offshore wind farm's location in Danish North Sea
Danish Energy Agency

Danish transmission system operator Energinet has issued a contract notice for the procurement of the onshore export cable section for the 1 GW Thor offshore wind farm.

The wind farm’s onshore grid connection consists of 21 individual cable sections each containing two 220 kV cable systems with a combined length of approximately 28 kilometres. The total length of the single core cable for Thor is approximately 175 kilometres, Energinet said.

Additionally to cable production and delivery, the contract also includes the supervision of civil works, performed by a third-party contractor, and cable pulling, manufacturing, delivery, and installation of joints and terminations, as well as final commissioning testing.

The delivery, installation, and testing of the onshore export cable system is anticipated to take place in 2024.

The contract is valued at EUR 17 million. The tender will remain open until 28 March.

Scheduled for full commissioning in 2027, the subsidy-free Thor offshore wind farm will be developed and operated for a period of 30 years by Germany’s RWE.

Related Articles

News

RWE Signs Thor Concession Agreement with Danish State

2 min read

The wind farm is located in the North Sea, west of the Jutland peninsula and some 20 to 45 kilometres west of the coastal village Thorsminde.

Energinet plans to have the grid connection for Thor ready by 1 January 2025. The wind farm’s export cable system will make landfall at Tuskær, north of Nissum Fjord.

NOTE: The original article has been amended.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Contracts & TendersGrid ConnectionWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1X1 Wind Closes Strategic Funding Round Ahead of 8.5 MW Floater Deployment
  2. 2RWE, Masdar Team Up for 2027 German Offshore Wind Auctions
  3. 3European Project Completes First Tests of Modular Drivetrain for Offshore Wind Turbines Beyond 15 MW
  4. 4Ørsted Gets Final Opinion in Double Taxation Case Over Two UK Offshore Wind Farms