Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Subsea 7 Plants First Cables for Hywind Tampen Floating Offshore Wind Farm
Grid Connection

July 22, 2022 · about 4 years ago

Subsea 7 Plants First Cables for Hywind Tampen Floating Offshore Wind Farm

Subsea 7 has laid the first subsea cables in the water for the 94.6 MW Hywind Tampen floating wind farm offshore Norway. JDR Cable System is in charge of supplying the electric cables for the project from its factory in Hartlepool, the UK, while Subsea 7 is responsible for the installation of the ca

2 minutes read
  • LinkedIn
  • X
  • Email
Subsea 7 Hywind Tampen
Subsea 7 Hywind Tampen

Subsea 7 has laid the first subsea cables in the water for the 94.6 MW Hywind Tampen floating wind farm offshore Norway.

JDR Cable System is in charge of supplying the electric cables for the project from its factory in Hartlepool, the UK, while Subsea 7 is responsible for the installation of the cables and the connection to the Snorre A and B and Gullfaks A, B and C oil and gas platforms.

JDR has completed the first of multiple load-outs of dynamic subsea cables for the floating offshore wind project.

The load-out consisted of five terminated cables each with pull-in-head arrangements on either end from carousel storage located within the facility.

The floating wind project entered the offshore construction phase in March with the transport and installation of the suction anchors at the site located about 140 kilometers off the Norwegian coast.

Hywind Tampen will comprise 11 Siemens Gamesa 8 MW wind turbines installed on concrete SPAR-type floating foundations in water depths of between 260 and 300 metres.

Once commissioned by the end of 2023, Hywind Tampen will become the largest floating offshore wind farm in operation.

The project was initially scheduled to be completed by the end of 2022, but due to some deviations found in steel quality in four tower sections and supply chain bottlenecks, the first seven wind turbines will come on stream this year as planned, while the final four will be installed next spring, according to Equinor.

Related Articles

Wind Farm Update

Faulty Towers Set World’s Largest Floating Offshore Wind Farm Back

2 min read

Equinor is developing and will operate the NOK 5 billion (EUR 488 million) wind farm on behalf of the partnerships which include Equinor Energy AS, Petoro AS, and OMV (Norge) AS for the Gulflaks license, and Equinor Energy AS, Petoro AS, Idemitsu Petroleum Norge AS, Wintershall Dea Norge AS, and Vår Energi AS for the Snorre license.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Offshore Charging, Rare Earth Magnet Projects Secure EU Funding
  2. 2Terna Energy Plans 45 MW Floating Wind Pilot in Greece
  3. 3Kumagai Gumi Joins DemoSATH as Floating Wind Test Project Extended Through 2027
  4. 4New Zealand Opens First Offshore Wind Feasibility Permit Round

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free