Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›Final Foundation In Place at Hollandse Kust Zuid
Ports & Logistics

September 9, 2022 · about 4 years ago

Final Foundation In Place at Hollandse Kust Zuid

Seaway Heavy Lifting and Sif have completed the installation of all 140 monopile foundations at the 1.5 GW Hollandse Kust Zuid in the Dutch North Sea. The foundations were installed in two campaigns. The first campaign ended in December 2021 with 34 foundations installed. The remaining 106 foundatio

1 minutes read
  • LinkedIn
  • X
  • Email
Final Foundation In Place at Hollandse Kust Zuid
Vattenfall

Seaway Heavy Lifting and Sif have completed the installation of all 140 monopile foundations at the 1.5 GW Hollandse Kust Zuid in the Dutch North Sea.

The foundations were installed in two campaigns. The first campaign ended in December 2021 with 34 foundations installed.

Related Articles

Ports & Logistics

First Installation Campaign at Largest Offshore Wind Farm Under Construction Falls Short

3 min read

The remaining 106 foundations were installed in the second campaign which started this Spring.

The monopile foundations without transition pieces were transported from Sif’s yard on the Maasvlakte and installed at the site some 20 kilometres off the Dutch province of Zuid-Holland by the heavy-lift vessel Seaway Strashnov .

”A big achievement by the project team, our contractors – Seaway Heavy Lifting & SIF – and all other parties involved. Going from installing 34 foundations in the 2021 summer campaign, to installing 106 foundation in 2022, is a huge testament to the team,” Mary Carol Anderson , foundation installation manager, said.

Hollandse Kust Zuid, the world’s first subsidy-free offshore wind farm and soon to be the world’s largest operating offshore wind farm, comprises 140 Siemens Gamesa 11.0-200 DD wind turbines scheduled to be installed by March 2023.

The wind farm generated first power in early August.

Related Articles

Wind Farm Update

Subsidy-Free Offshore Wind Power Starts Flowing into Dutch Grid

2 min read

Vattenfall is leading the development of the project.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free