Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Australian State Starts Planning Offshore Wind Grid Development
Authorities

April 11, 2023 · about 3 years ago

Australian State Starts Planning Offshore Wind Grid Development

VicGrid, a new body established by the government of the Australian state of Victoria that coordinates the overarching planning and development of the state’s renewable energy zones (REZ), has initiated early consultation on new transmission connections for offshore wind with an aim to select prefer

2 minutes read
  • LinkedIn
  • X
  • Email
An image showing Portland connection point area of interest for investigation on a map
Portland connection point area of interest for investigation; Source: Offshore Wind Transmission Development and Engagement Roadmap; VicGrid

VicGrid, a new body established by the government of the Australian state of Victoria that coordinates the overarching planning and development of the state’s renewable energy zones (REZ), has initiated early consultation on new transmission connections for offshore wind with an aim to select preferred transmission options or concepts by the end of this year.

Last month, VicGrid issued a Development and Engagement Roadmap that sets out our key steps to be taken this year to plan new offshore wind transmission through engagement with local communities and key stakeholders.

Through the process, VicGrid will determine potential new transmission connection points and transmission corridors to enable a coordinated connection of offshore wind farms in Gippsland and Portland.

As reported in March, Victorian Energy and Resources Ministery released the Victorian Offshore Wind Energy Implementation Statement 2 which sets out how the state will leverage industry-led investment in offshore wind for the first tranche of projects that will deliver at least 2 GW by 2032, as per the Victorian government’s targets.

The strategy, among other things, outlines that VicGrid will lead the development of transmission infrastructure for offshore wind, with specific transmission connection point locations and route corridors in Gippsland and Portland to be announced by the end of 2023.

Related Articles

Authorities

Victoria Issues Offshore Wind Implementation Statement

3 min read

“For offshore wind to succeed we need to expand our electricity transmission system to connect this new clean energy source to Victorian homes and businesses across the state. Our role on offshore wind is to ensure new transmission is available in time to make use of this new clean energy source and meet Victoria’s offshore wind targets” , VicGrid states in an invitation for public comment.

According to Victoria’s REZ manager, the transmission solution will involve avoiding multiple transmission lines overlapping the landscape from offshore wind projects, reducing duplication and cumulative impacts to regional communities hosting the new transmission, and avoiding unnecessary energy costs for Victorian households and businesses.

The Gippsland area is Australia’s first offshore wind area , following the country’s Minister for Climate Change and Energy declaring the Bass Strait as suitable for offshore renewable energy infrastructure.

The area already has several projects proposed to be built there, including the 2 GW Star of the South , Australia’s first and most progressed offshore wind project and the first offshore wind project to receive Major Project Status from the Australian government.

In January of this year, the country’s Ministry for Climate Change and Energy opened the invitation period for feasibility licence applications for the Gippsland area, which closes on 27 April.

Related Articles

Authorities

Australia’s First Offshore Wind Zone Open for Feasibility Licence Applications

2 min read

As for Victoria, the state’s government has set targets of at least 2 GW of offshore generation capacity by 2032, 4 GW by 2035 and 9 GW by 2040.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

AuthoritiesGrid Connection

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free