Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fixed-Bottom›First Coastal Virginia Offshore Substation Arrives in Denmark
Fixed-Bottom

January 23, 2024 · about 2 years ago

First Coastal Virginia Offshore Substation Arrives in Denmark

The first of three 880 MW offshore substations being built for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project has arrived at the Bladt Industries production site in Aalborg, Denmark, for outfitting from a prefabrication site in Spain. In 2021, a consortium comprising Semco Maritime

2 minutes read
  • LinkedIn
  • X
  • Email
Bladt Industries Semco CVOW Substation
Source: Bladt Industries, LinkedIn; First CVOW substation

The first of three 880 MW offshore substations being built for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project has arrived at the Bladt Industries production site in Aalborg, Denmark, for outfitting from a prefabrication site in Spain.

In 2021, a consortium comprising Semco Maritime and Bladt Industries was awarded a contract for the supply of three substations for the 2.6 GW CVOW offshore wind project in the US.

Related Articles

Contracts & Tenders

Semco, Bladt to Deliver Offshore Substations for Virginia’s 2.6 GW OWF

2 min read

Denmark-headquartered Bladt Industries is responsible for the design, procurement, and manufacturing of the steel structures and jacket foundations for the substations, while the design, procurement, and installation of electrical equipment, energy systems, and inter-array cables will be managed by Semco Maritime.

Along with the substations’ steel structures and foundations, Bladt will also deliver the transition pieces (TPs) for the offshore wind farm’s wind turbine foundations under a separate contract secured with the developer.

When it is done, each 880 MW offshore substation will weigh 3,800 tonnes, not including the jacket foundations or the pin piles.

As previously reported, Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant (BoP) contractors for the transportation and installation of the foundations and the substations and the engineering, procurement, construction, and installation (EPCI) services for the inter-array and export cables for the project.

DEME Offshore will oversee the complete offshore installation works for the foundations, substations, and infield cables, as well as part of the export cables.

Prysmian Group will provide the export cables and 320 kilometres of 3-core 66 kV offshore inter-array cables with XLPE insulation for the wind farm.

YOU MIGHT ALSO LIKE

The CVOW project will comprise 176 Siemens Gamesa 14 MW wind turbines and three offshore substations in the 112,800-acre commercial lease area located 27 miles (about 43 kilometres) off the Virginia Beach coast.

Construction and fabrication activities are already underway, with the monopile foundations arriving at the Portsmouth Marine Terminal in Virginia. The installation of foundations and wind turbines is scheduled to begin in 2024.

Once fully constructed in 2026, the 2.6 GW offshore wind farm will be able to generate enough electricity to power up to 660,000 households.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Fixed-BottomGrid ConnectionManufacturingOffshore PlatformsProject UpdatesSupply ChainWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  2. 2Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  3. 3All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  4. 4Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free