Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fixed-Bottom›Pre-Construction Work Underway at East Anglia Three Offshore Wind Farm Site
Fixed-Bottom

December 26, 2024 · about 1 year ago

Pre-Construction Work Underway at East Anglia Three Offshore Wind Farm Site

A pre-installation survey at the East Anglia Three offshore wind farm site is scheduled to begin in early January 2025, following subsea boulder clearance and scour protection work that was carried out in November 2024 and marked the start of offshore construction work. The survey, which will be per

2 minutes read
  • LinkedIn
  • X
  • Email
Pre-Construction Work Underway at East Anglia Three Offshore Wind Farm Site
Source: Glomar Offshore

A pre-installation survey at the East Anglia Three offshore wind farm site is scheduled to begin in early January 2025, following subsea boulder clearance and scour protection work that was carried out in November 2024 and marked the start of offshore construction work.

The survey, which will be performed by Seaway7 and Beam using the vessel Glomar Worker , is expected to be completed by the end of January, according to a Notice to Mariners from ScottishPower Renewables.

The offshore pre-construction activities at the East Anglia Three site, located 69 kilometres off the Norfolk coast, began in early November with the relocation of boulders and non-geological debris, for which Seaway7 deployed the vessel Glomar Wave .

Around the same time, the company, in cooperation with Boskalis, mobilised the fallpipe vessel Rockpiper to install scour protection at the locations where wind turbine and offshore substation foundations will be installed.

The 1.4 GW East Anglia Three will comprise 95 Siemens Gamesa 14+ MW wind turbines , all of which are expected to be operational in 2026.

Seaway7 signed a contract in June 2023 for the transport and installation of 95 monopile foundations, associated seabed preparation and scour protection, and the engineering, supply, and installation of the inter-array cables.

Related Articles

Business & Finance

Seaway7 Signs USD 500+ Million Contract for East Anglia Three Offshore Wind Farm

2 min read

Haizea Wind Group and the Navantia-Windar consortium are manufacturing the monopile foundations and transition pieces for the project, while the inter-array cables will be supplied by Hellenic Cables.

The 1.4 GW East Anglia Three is the second of ScottishPower Renewables’ East Anglia offshore wind farms to be developed and part of the East Anglia Hub which includes two other offshore wind farms: the 800 MW East Anglia One North and the 900 MW East Anglia Two .

The wind farm was awarded a Contract for Difference in July 2022 and ScottishPower, owned by Spanish Iberdrola, started onshore construction work the same month.

Reach your target audience in one move! offshoreWIND.biz is read by thousands of offshore wind professionals daily.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Fixed-BottomProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ampelmann Completes Cargo Drone Campaign at Triton Knoll Offshore Wind Farm
  2. 2ACOUSTISCAN: Acoustic Partial Discharge Monitoring Strengthens Offshore Wind Reliability
  3. 3ABL to Support Marine Operations at Gennaker Offshore Wind Farm
  4. 4Dong Fang Offshore Takes Delivery of First Newbuild SOV, Adds New Vessel Order with Vard

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free