Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Aker Solutions Wins Contract for 2 GW German Offshore Wind Project
Business & Finance

February 11, 2025 · about 1 year ago

Aker Solutions Wins Contract for 2 GW German Offshore Wind Project

Aker Solutions has signed a contract with Spain’s Dragados Offshore to deliver the steel substructure for the 2 GW BalWin1 converter station in the German North Sea. The contract also includes an option for the BalWin2 steel substructure. The contract is worth between NOK 1.5 billion (approximately

2 minutes read
  • LinkedIn
  • X
  • Email
Aker balwin
Source: Aker Solutions

Aker Solutions has signed a contract with Spain’s Dragados Offshore to deliver the steel substructure for the 2 GW BalWin1 converter station in the German North Sea. The contract also includes an option for the BalWin2 steel substructure.

The contract is worth between NOK 1.5 billion (approximately EUR 130 million) and NOK 2.5 billion (about EUR 216 million), as per Aker Solutions’ definition of a significant contract.

The scope of work includes procurement, method engineering, and construction of offshore high-voltage direct current (HVDC) converter platform substructures.

Fabrication of the HVDC foundations will be carried out by Aker Solutions’ yard in Verdal, Norway, and at its peak, the project will employ over 500 people, according to the company.

Preparation for procurement and method engineering will commence immediately, while construction is planned to start in early 2026, with deliveries in 2028 and 2029.

Amprion Offshore is the transmission system operator (TSO) responsible for these systems. In 2023, the TSO awarded Siemens Energy and Dragados Offshore a contract to build converter stations for Germany’s BalWin1 and BalWin2 grid connections.

Under the contract, Dragados Offshore is responsible for the construction and offshore installation of the associated platforms.

Related Articles

Contracts & Tenders

Siemens Energy Consortium Nets EUR 4 Billion Offshore Wind Power Grid Deal

2 min read

The grid interconnection points for BalWin1 and BalWin2 will be in Wehrendorf (southern Osnabrück region) and Westerkappeln (northern North Rhine-Westphalia), respectively.

With transmission and transport capacity of 2 GW each, i.e., a total of 4 GW, these projects will be able to power a major city of four million people like Berlin, said Aker Solutions.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceContracts & TendersFoundationsGrid ConnectionManufacturingOffshore PlatformsSupply Chain

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free