Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Fabrication Starts on Germany’s First 2 GW Offshore Grid Connection System
Grid Connection

March 3, 2025 · about 1 year ago

Fabrication Starts on Germany’s First 2 GW Offshore Grid Connection System

The first steel has been cut for BalWin4, Germany’s first 2 GW offshore grid connection, at Sangsangin Ship Machinery’s factory in South Korea. The fabrication of the foundation for the topside that will later bring renewable energy from the North Sea to Germany has started. According to Daniel Birk

1 minutes read
  • LinkedIn
  • X
  • Email
BalWin4 first steel
Source: Sangsangin Ship Machinery via LinkedIn

The first steel has been cut for BalWin4, Germany’s first 2 GW offshore grid connection, at Sangsangin Ship Machinery’s factory in South Korea.

The fabrication of the foundation for the topside that will later bring renewable energy from the North Sea to Germany has started.

According to Daniel Birkenstock, project director at TenneT, this is the start of production of steel panels, which will be shipped after production to Batam, Indonesia, where McDermott International will assemble the topside.

McDermott International is responsible for the design, fabrication, installation, and commissioning of the offshore converter substation platforms for two 2 GW HVDC grid connection systems, BalWin4 and LanWin1, under a contract signed with TenneT in 2023.

The commissioning date for BalWin4 is 2029, while LanWin1’s fabrication, installation, and commissioning follow a year later, reaching completion in 2030, according to the company.

The consortium of Jan De Nul, LS Cable, and Denys will realize the cable connections in Lower Saxony, to BalWin4 and LanWin1, both to be connected in Unterweser area, and LanWin5 in the Rastede area, Germany.

The platforms’ main objective is to convert up to 2 GW of offshore wind-generated electricity from 66 kV alternating current to 525 kV direct current to facilitate efficient electricity transmission to the onshore station.

Related Articles

Cables

Cable Production Kicks Off for TenneT’s 2 GW Grid Connection Projects

2 min read

LinkedIn X Facebook Google News

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionOffshore Platforms

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1German Offshore Wind Vessel Operator Acquires 50 Pct Stake in Norwegian Crewing Company
  2. 2Dajin Heavy Industry Adds Third Large Deck Transport Vessel to Its Fleet
  3. 3Tekmar Nets EUR 6 Million Contract Extension in Offshore Wind
  4. 4Subsea Micropiles to Invest GBP 5 Million in Expanding Manufacturing, Offshore Ops at Scottish Port

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free