PGE O&M base

PGE Baltica Contracts Local Company to Build O&M Base for Polish Offshore Wind Farms

Business & Finance

PGE Baltica, owned by PGE Polska Grupa Energetyczna, has selected local company Doraco as the general contractor of the operational and service (O&M) base for the offshore wind farms in Ustka, Poland.

The O&M base will consist of an office and warehouse building, a maneuvering area, and a quay where service units will moor to transport crews to the offshore wind farm area.

The commissioning of the base is planned for the fourth quarter of 2026.

PGE Baltica has secured a building permit for the Ustka investment. The company also selected a contract engineer, Sweco Polska, responsible for supervising the detailed design and construction of the O&M base.

The new PGE Baltica facilities in Ustka will be built on an area of approximately 2.3 hectares on the western side of the Słupia River.

The first wind farm operated from the Ustka base will be Baltica 2, which PGE is building together with its partner Ørsted.

Located approximately 40 kilometres off the Polish coast near Ustka, the 1.5 GW offshore wind farm will comprise 107 Siemens Gamesa 14 MW-222 turbines.

Baltica 2 is expected to be fully commissioned by the end of 2027. With a joint capacity of 2.5 GW, the Baltica 2 and Baltica 3 projects will create the Baltica Offshore Wind Farm. Baltica 3 is planned to be fully operational by the end of the decade.