The 66 kV subsea array cables are manufactured by UK-based JDR under a contract signed with Seaway7 in August 2022.
The internal wind farm cabling will later be connected to the converter platform managed by the transmission system operator (TSO) TenneT, which is planned to be installed offshore in the summer.
From there, the generated electricity will be converted from alternating current to direct current and brought ashore using two high-voltage DC export cables.
The He Dreiht project is expected to soon enter the wind turbine installation phase, as all monopile foundations were installed at the project site located around 90 kilometres northwest of the island of Borkum in the summer of 2024.
The 960 MW wind farm will comprise 64 V236-15.0 MW wind turbines provided by Vestas. The project is expected to generate enough electricity to meet the needs of around 1.1 million households.