Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Storage›RWE Takes FID on 400 MW Battery Storage to Support Dutch OranjeWind Offshore Wind Farm
Storage

September 21, 2026 · 1 hour ago

RWE Takes FID on 400 MW Battery Storage to Support Dutch OranjeWind Offshore Wind Farm

AB

Adrijana Buljan

Offshore Wind

2 minutes read
  • LinkedIn
  • X
  • Email
RWE's large-scale battery energy storage system in Eemshaven
Illustration; Large-scale battery energy storage system in Eemshaven; Photo source: RWE

RWE has taken the final investment decision (FID) to build a 400 MW/1,100 MWh battery energy storage system at its Moerdijk power station in the Netherlands as part of the system integration solutions for the 795 MW OranjeWind offshore wind farm being developed with TotalEnergies.

The battery will comprise 208 lithium-ion battery containers and will be able to deliver its full 400 MW output for almost three hours. Construction is scheduled to start in due course, with commissioning planned for the second quarter of 2028, RWE said on 21 September.

OranjeWind, also known as Hollandse Kust West VII, is being built approximately 53 kilometres off the Dutch coast and will comprise 53 Vestas V236-15.0 MW turbines.

Offshore construction has already started, with monopile installation currently underway.

Related Articles

Environment

First Monopile Installed at RWE and TotalEnergies’ Dutch Offshore Wind Farm

2 min read

Turbine installation is planned for 2027, and the wind farm is scheduled to become operational in 2028.

The new battery will be connected to the national grid through the existing substation at RWE’s Moerdijk power plant. Under capacity steering agreements with transmission system operator TenneT, it will be dispatched to relieve grid congestion in Noord-Brabant and create additional capacity for parties currently on the grid connection waiting list. The battery will also provide grid services, including instantaneous reserve.

RWE already operates a 7.5 MW/11 MWh battery at Moerdijk, also developed as part of OranjeWind’s system integration package, which entered commercial operation in June 2025.

Related Articles

Fixed-Bottom

RWE Commissions First of Two Battery Energy Storage Systems as Part of OranjeWind Project

2 min read

OranjeWind’s system integration package also includes electrolysers, e-boilers and smart charging, as part of the tender requirements for the offshore wind farm site, which RWE secured in 2022.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

StoragePower-to-XProject UpdatesProject UpdatesWind Farm UpdateFixed-BottomBusiness & Finance

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Gennaker Offshore Substation Topsides Loaded Out Ahead of Sail-Away
  2. 2RWE Takes FID on 400 MW Battery Storage to Support Dutch OranjeWind Offshore Wind Farm
  3. 3Gazelle Tests Floating Wind Platform for 18+ MW Turbines in Typhoon Conditions
  4. 4US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free