Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Project Updates›China Three Gorges Connects First Qingzhou V & VII Offshore Wind Turbines to Grid
Project Updates

September 30, 2026 · 1 hour ago

China Three Gorges Connects First Qingzhou V & VII Offshore Wind Turbines to Grid

AB

Adrijana Buljan

Offshore Wind

2 minutes read
  • LinkedIn
  • X
  • Email
Qingzhou V & VII Offshore Wind Farm converter station
Qingzhou V & VII Offshore Wind Farm converter station; Source: CTG

China Three Gorges Corporation (CTG) has connected the first batch of turbines at its 2 GW Qingzhou V & VII offshore wind project off Yangjiang, Guangdong Province, to the grid.

The first turbines were connected on 27 September, according to CTG.

The project is located approximately 70 kilometres offshore and comprises 163 wind turbines, with individual turbine capacities of more than 12 MW.

The project’s 2 GW transmission system uses a ±500 kV flexible high-voltage direct current (HVDC) connection, with electricity collected offshore and transmitted to an onshore control centre through two HVDC subsea cables.

CTG says Qingzhou V & VII is the world’s first large-scale offshore wind flexible HVDC transmission project and the first application of ±500 kV DC subsea cables for offshore wind. The system also has the highest voltage level and largest transmission capacity among offshore wind flexible HVDC projects, according to CTG.

The installation of the 25,000-tonne converter platform for the Qingzhou V & VII was completed this summer by COSCO Shipping Specialized Carriers.

Related Articles

Fixed-Bottom

COSCO Installs 2 GW Offshore Converter Platform for China’s New Wind Farm

1 min read

Known as the “Heart of Offshore Wind”, the converter station receives electricity collected from the wind turbines at 66 kV AC, converts and steps it up to ±500 kV DC, and sends it to shore.

The wind farm uses 30 66 kV inter-array cable circuits, with five or six turbines connected to each circuit. One of the connections is a dynamic 66 kV cable linking the 16 MW floating wind turbine to the network.

Related Articles

Business development

China Three Gorges Installs ‘World’s Largest’ Single-Unit Floating Wind Platform Offshore Yangjiang

2 min read

The project’s ±500 kV HVDC export system consists of one circuit comprising two subsea cables. Each cable is approximately 91 kilometres long and has a conductor cross-section of 2,500 mm², according to Orient Cable (NBO), which said it delivered the HVDC subsea cable system under an EPCI scope.

The wind turbines at Qingzhou V & VII, supported by four-legged jacket foundations, were installed in 14 months, after the installation started in May 2025. During the peak construction period, up to eleven large vessels were operating simultaneously and 23 turbines of 12 MW or larger were installed in a single month, the developer said. 

The 2 GW offshore wind farm is expected to generate approximately 6 TWh of clean electricity annually once fully operational, according to CTG, avoiding around 5 million tonnes of carbon dioxide emissions per year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Project UpdatesProject UpdatesWind Farm UpdateFixed-BottomOffshore PlatformsGrid Connection

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Victoria Identifies Preferred Transmission Route for First Offshore Wind Projects
  2. 2China Three Gorges Connects First Qingzhou V & VII Offshore Wind Turbines to Grid
  3. 3Ørsted's First UK Offshore Wind Farm Marks 20 Years of Operation
  4. 4German Offshore Wind Vessel Operator Acquires 50 Pct Stake in Norwegian Crewing Company

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free