Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm
Wind Farm Update

October 13, 2026 · 2 hours ago

Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm

AB

Adrijana Buljan

Offshore Wind

1 minutes read
  • LinkedIn
  • X
  • Email
Seaway Phoenix vessel at sea
Seaway Phoenix; Photo source: Seaway7

Seaway7 is expected to start installing inter-array cables at the Hornsea 3 offshore wind farm site in the UK in the coming days.

According to a recently issued project operation notice from Ørsted, cable-laying vessel (CLV) Seaway Phoenix is loading cable in Eemshaven, the Netherlands, and is planned to arrive at the UK site on 19 October. Seaway Moxie will support the work and is currently also in Eemshaven, mobilising before sailing to the Hornsea 3 site on 15 October.

Grand Canyon 3 will start mobilising from Blyth, the UK, on 17 October for pre-trench survey and trenching operations, and is scheduled to start operations at the site on 20 October.

Hornsea 3 is being built some 120 kilometres off the Norfolk coast, where 197 Siemens Gamesa’s 14 MW turbines will be installed.

Seaway7 was contracted for the transport and installation of the inter-array cables at the 2.9 GW offshore wind farm in 2024.

Related Articles

Business & Finance

Seaway7 to Wire Ørsted’s Hornsea 3 Offshore Wind Farm

2 min read

Hellenic Cables and Prysmian Group will supply the cables, while JDR Cable Systems is in charge of array cable testing and termination.

At the Hornsea 3 site, construction is already underway, with the project’s second offshore converter station installed in September, after the installation of the wind farm’s 197 monopile foundations began earlier this year.

Related Articles

Project Updates

Sleipnir Installs Second Hornsea 3 Offshore Substation

1 min read

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm UpdateProject UpdatesProject UpdatesFixed-BottomCablesVessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm
  2. 2Ørsted Orders Third Saab Seaeye Cougar ROV for Offshore Wind Operations
  3. 3Hampidjan Advant to Equip Cadeler's Wind Ace for East Anglia Two Job
  4. 4OEG to Supply Temporary Power for Hornsea 3 Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free