348 results found for 'DolWin3'

348 results found for 'DolWin3'
Order results by

A list of search results

  • 27 August 2024
    Contracts & Tenders, Fixed-Bottom, Grid Connection, Offshore Platforms, Operations & Maintenance, Supply Chain, Vessels

    TenneT has invited tenders for the provision of a platform supply vessel (PSV) and crew to conduct supply tours to TenneT’s offshore platforms in the German North Sea. According to a contract notice issued on 21 August, the transmission system operator (TSO) will award a multiple-year charter contract for an initial duration of five years, […]

  • 5 November 2024
    Grid Connection, Project Updates, Wind Farm Update

    The 900 MW Borkum Riffgrund 3 offshore wind farm in Germany will be commissioned in the first quarter of 2026 instead of the initially planned fourth quarter of 2025 due to a delay in the grid connection construction. According to information that Borkum Riffgrund 3 developer, Ørsted, shared in its third-quarter 2024 report, the installation […]

  • 10 July 2024
    Business & Finance, Grid Connection, Offshore Platforms

    Dutch engineering company Iv has designed more than a quarter of all offshore wind platforms in the European Union, the company said on 9 July, citing offshore wind statistics from a WindEurope report. Of the 19 GW of offshore wind energy the EU had installed at the end of 2023, Iv has worked on offshore […]

  • 19 June 2024
    Grid Connection, Infrastructure, Offshore Platforms

    The construction of the DolWin4 and BorWin4 offshore grid connection projects in Northern Germany has commenced, Amprion said on 18 June. Work on the DolWin4 and BorWin4 offshore grid connections, which will transport power from offshore wind farms in the North Sea to the mainland, has started in Lingen and Wietmarschen, where construction camps are […]

  • 17 October 2024
    Business & Finance, Contracts & Tenders, Grid Connection, Manufacturing, Offshore Platforms, Supply Chain

    German transmission system operator (TSO) Amprion has selected TÜV SÜD as the Owner’s Engineer to supervise the construction of the converter platforms for the BorWin4 and the DolWin4 offshore grid connection systems. The contract covers overseeing the fabrication of the platforms’ individual components at several locations worldwide, such as supervision of the fabrication of large […]

  • 7 May 2024
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    ZTT Submarine Cable & System has finished the installation and termination of the 155 kV submarine cable connecting the Gode Wind 3 offshore wind farm to the DolWin kappa offshore converter platform in Germany. In 2020, TenneT contracted ZTT Submarine Cable & System to link the 253 MW offshore wind farm to the DolWin kappa […]

  • 19 June 2024
    Business & Finance, Industry

    Global energy consultancy Xodus has established a new dedicated offshore renewables engineering arm, named Evolv Energies, to strengthen its capabilities in the offshore markets. Evolv Energies has been created to deliver broader engineering services as the development of renewables projects ramp up globally, said Xodus. The new entity targets energy transition contracts in the concept […]

  • 17 June 2024
    Fixed-Bottom, Vessels

    China-based Tier 1 supplier to the offshore wind industry, ZTT, will put its flagship monopile installation vessel Zhongtian 39, launched in October 2023, through an upgrade to prepare the vessel “to take on its next mission with unmatched capabilities”. The upgrade will include the integration of a DP2 dynamic positioning system into the vessel which […]

  • 25 June 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The German Federal Maritime and Hydrographic Agency (BSH) has issued the planning approvals for Nordseecluster A, the first phase of RWE’s Nordseecluster offshore wind project. The Nordseecluster offshore wind project is being built around 46 kilometres north of the German island of Borkum and approximately 50 kilometres north of the German island of Juist. The […]

  • 19 July 2024
    Contracts & Tenders, Grid Connection, Offshore Platforms, Onshore Infrastructure, Supply Chain

    The transmission system operator (TSO) 50Hertz has awarded the consortium comprising Dragados Offshore, a subsidiary of Cobra IS, and Siemens Energy a EUR 2.9 billion contract to design, build, and install two electrical conversion stations. The consortium’s scope of work consists of supplying an offshore converter for the LanWin3 grid connection project in the North […]

  • 19 March 2024
    Business & Finance, Cables, Fixed-Bottom, Grid Connection

    TenneT and Nexans, which signed framework agreements for three offshore grid connections last year, have now signed a call-off contract for the BalWin3 and LanWin3 projects, each of which will have a capacity of 2 GW and will link offshore wind farms to the German grid. In May 2023, TenneT awarded NKT, Nexans, and a […]

  • 20 March 2024
    Grid Connection, Market Outlooks, Outlook & Strategy

    Great Britain’s electricity system operator (ESO) has proposed a GBP 58 billion (approximately EUR 68 billion) investment in the electricity grid. The proposal outlines a vision for incorporating an additional 21 GW of offshore wind into the grid by 2035, which would bring the country’s total offshore wind capacity to a potential 86 GW. The […]

  • 16 June 2017
    Grid Connection

    The topside of the DolWin gamma offshore converter station has sailed out of the Nordic Yard facility in Rostock to the German North Sea, TenneT reports.

  • 10 April 2015
    Grid Connection

    TenneT has issued two invitations to tender for the DolWin3 offshore grid connection. The first one is for the manufacture, supply and installation of an AC submarine cable system (including compensation, fibre optic cable, secondary equipment, cable performance, etc.) between an offshore wind farm and Cluster 2, designed for a transmission capacity of approximately 450MW and a voltage level […]

  • 29 May 2017
    Grid Connection, Technology

    The DolWin gamma offshore platform is ready to sail out to the German North Sea after completing all the necessary testing at the Nordic Yard facility in Rostock, according to General Electric (GE).

  • 24 August 2016
    Grid Connection, Technology

    SeaTerra GmbH has completed investigation of 278 objects and removal of eight unexploded ordnance (UXO) targets from the DolWin3 cable route in the German part of the North Sea. Commissioned by the transmission system operator TenneT, SeaTerra GmbH recently examined and cleared numerous metal objects from the future DolWin3 cable route between Emden and the […]

  • 21 September 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for Structural Health Monitoring systems (SHM systems) and their installation on twelve offshore HVDC platforms, including both existing and platforms yet to be installed offshore. Under a five-year, EUR 3.25 million contract, the tender winner will develop and install a monitoring concept for the support structures of the […]

  • 28 March 2022
    Contracts & Tenders, Grid Connection

    VCE Vienna Consulting Engineers ZT has been awarded a contract to install Structural Health Monitoring (SHM) systems on twelve TenneT’s HVDC platforms in Germany. On nine platforms, which are in operation, the installation of the SHM systems will be carried out offshore during operation, while for the three platforms which are under construction or in […]

  • 7 July 2017
    Grid Connection

    The topside of the DolWin gamma offshore converter station has been installed next to the DolWin alpha in the German part of the North Sea, according to TenneT.

  • 20 July 2015
    Grid Connection, Technology

    Alstom and Nordic Yards have installed two 700 MVA power transformers on the DolWin3 converter platform based in the Warnemüde shipyard in Germany, operated by Nordic Yards. The transformers were designed and built by Alstom specifically for the DolWin3 converter project at its Mönchengladbach plant in Germany. During routine inspections, one transformer can continue to […]

  • 4 November 2020
    Contracts & Tenders, Grid Connection

    TenneT has invited tenders for services related to cable repair and maintenance in both Germany and the Netherlands, which include locating cable faults. The services will be delivered across several grid connections and interconnectors. The transmission system operator (TSO) is looking to conclude a contract for a service-level agreement with a provider of cable fault […]

  • 4 March 2013

    Germany: Siemens Reports Delay on Sylwin 1 Transformer Platform Siemens has announced that the connection of a German offshore wind farm in the North Sea will be delayed.   UK: Dogger Bank Receives First Bucket Foundation The installation of the first of two innovative suction-installed foundations on Dogger Bank on the weekend represents the first […]

  • 26 February 2013
    Business & Finance, Grid Connection

    Transmission System Operator TenneT has awarded the DolWin3 offshore project to Alstom. This project connects the North Sea wind farms to the mainland supergrid and has an investment volume of more than €1 billion. “With this project, we help to take the energy turnaround another step forward and make it possible for offshore wind energy […]

  • 13 November 2019
    Grid Connection

    Italian subsea cable specialist Prysmian has completed the DolWin3 High Voltage Direct Current (HVDC) offshore grid connection project in the German North Sea. Prysmian had secured this project in February 2013, with a contract awarded by Alstom Grid (now GE Grid GmbH) on behalf of the Dutch-German grid operator TenneT. DolWin3, the third offshore grid […]

  • 2 September 2020
    Contracts & Tenders, Grid Connection, Vessels

    TenneT has selected Seafox to provide an accommodation jack-up barge for operations on DolWin Alpha and DolWin Gamma offshore platforms in Germany. The transmission system operator (TSO) was looking for an offshore jack-up barge that could accommodate up to 47 persons on board (POBs) in single cabin occupancy, with direct access to the DolWin Alpha […]

  • 14 April 2016
    Business & Finance, Environment, Grid Connection, Technology

    Multinational energy conglomerate General Electric (GE) is hoping the successful completion of the 900MW DolWin 3 offshore grid connection project will prove a good reference in the company’s future bids for German offshore wind projects, Reuters reports. Germany’s offshore wind sector ”has become very important” to GE, Carlos Haertel, CEO at GE Germany & Austria, was quoted by Reuters […]