145 results found for 'Formosa 1 Phase 1'

145 results found for 'Formosa 1 Phase 1'
Order results by

A list of search results

  • 15 November 2024
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    Formosa 4, Synera Renewable Energy’s (SRE) third offshore wind project in Taiwan, received the establishment permit from the Energy Administration, Ministry of Economic Affairs, in late October. According to SRE, Formosa 4 is the first project to reach this milestone among all successful bidders in the first auction for Phase 3 Zonal Development for Offshore […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 30 April 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Operations & Maintenance, Supply Chain

    James Fisher and Sons plc (James Fisher) has been awarded a contract for the provision of high voltage (HV) specialist personnel and HV safety management services at the 298 MW Zhong Neng offshore wind farm in Taiwan. Under the contract, worth over GBP 1 million (approximately EUR 1.17 million), James Fisher’s renewables team will securely […]

  • 20 December 2016
    Wind Farm Update

    Two Siemens 4MW turbines were installed off Taiwanese coast in October, representing the completion of the first phase of the Formosa 1 offshore wind farm, which is set to comprise 32 turbines by 2019.  Both the foundations and turbines were installed by using the vessel M/V TORBEN, formerly known as Friedrich Ernestine, owned by RWE Offshore […]

  • 21 April 2017
    Wind Farm Update

    Taiwan’s first two offshore wind turbines, set up as the first phase of the Formosa 1 offshore wind farm, are reportedly set to enter operations in May.

  • 15 October 2020
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    CWind Taiwan has been awarded a balance of plant (BOP) contract for the Formosa 1 offshore wind farm. The company is providing inspection and maintenance services to the 22 turbines at Formosa 1 Phase 1 and Formosa 1 Phase 2 sites, including internal and external inspections and painting. Under the contract, signed with Formosa 1 […]

  • 9 May 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    UK-based Tekmar Energy has supplied its TEKLINK Cable Protection System (CPS) to protect the underwater power cables as they enter the wind turbine foundations on the Formosa 1 Phase 1 project, the first offshore wind farm in Taiwan.

  • 7 January 2020
    Wind Farm Update

    The Formosa 1 offshore wind project in Taiwan started commercial operation on 27 December, according to JERA. The 128MW wind farm consists of the 8MW Formosa 1 Phase 1, inaugurated in May 2017, and the 120MW Formosa 1 Phase 2 which was officially commissioned in November. Formosa 1 comprises two Siemens Gamesa 4MW turbines from the first phase […]

  • 20 May 2019
    Wind Farm Update

    The Formosa 1 Phase 2 project has entered the construction phase following a groundbreaking ceremony held in Taiwan’s Miaoli County over the past weekend. Formosa 1 Phase 2 will comprise 20 Siemens Gamesa 6MW turbines installed on monopile foundations some 6km off the west coast of the Miaoli district in the Taiwan Strait. The project is owned by Formosa I Wind […]

  • 17 May 2018
    Contracts & Tenders, Wind Farm Update

    Jan De Nul has won a contract for the design, procurement and installation of the wind turbine foundations for the 120MW Formosa 1 Phase 2 wind farm offshore Taiwan.

  • 29 November 2019
    Business & Finance

    SeaPlanner, SeaRoc Group’s marine management system, has been selected to support the operations and maintenance phase of the Formosa 1 offshore wind farm in Taiwan. Under the 10-year contract, SeaPlanner will be deployed by the O&M team to coordinate all personnel and marine logistics for the 128MW wind farm. SeaPlanner also supported the construction of […]

  • 3 March 2020
    Vessels

    Penguin International Ltd. has delivered the service accommodation and transfer vessel (SATV) for the Formosa 1 offshore wind project to a Taiwanese operator. The 35m SATV Ventus Formosa was built by the Penguin Shipyard in Singapore and designed by the UK BMT. According to Penguin, the prototype vessel is purpose-built for 12 technicians to live […]

  • 25 July 2019
    Wind Farm Update

    Jack-up vessel Seajacks Zaratan has installed the first of the 20 Siemens Gamesa 6MW wind turbines on the 120MW Formosa 1 Phase 2 wind farm in Taiwan. The project is located around six kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30m. Seajacks […]

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 17 April 2019
    Wind Farm Update

    Ørsted has posted a photo showing the first wind turbine components destined for the Formosa 1 Phase 2 offshore wind farm lined up at the Taichung Port in Taiwan. The first 75m long blades, 378t nacelles and 37m long tower sections began their journey to Taiwan from Aalborg, Denmark, and Cuxhaven, Germany, on board three vessels. Formosa 1 Phase 2 will […]

  • 20 August 2019
    Contracts & Tenders

    UK-based Tekmar Energy Limited has secured two contracts within Taiwan for the supply of its TEKLINK® cable protection system and associated accessories. The combined value of the two contracts is circa GBP 4 million. Further details on the contracts will be provided in due course, Tekmar said. The two contract awards have come in addition to Tekmar’s earlier […]

  • 13 May 2019
    Vessels

    The self-propelled jack-up Seajacks Zaratan has arrived in Taichung, Taiwan, where the vessel will transport and install wind turbines on the 120MW Formosa 1 Phase 2 offshore wind farm. Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 turbines on the wind farm in the Taiwan Strait in what is the first renewables contract for Seajacks outside Europe. The turbine components have already […]

  • 8 August 2019
    Grid Connection, Wind Farm Update

    Jan De Nul’s cable-laying vessel Willem de Vlamingh has completed the installation of the export cables on the Formosa 1 Phase 2 offshore wind farm in Taiwan. Under the EPCI contract, Jan De Nul installed 17 inter-array and three export cables at the 120MW offshore wind farm. According to the company, at the beach landing, the […]

  • 23 April 2020
    Operations & Maintenance, Vessels

    Siemens Gamesa has inaugurated the world’s first Service Accommodation Transfer Vessel (SATV) in Taiwan. The 35-metre Ventus Formosa will operate from Taichung. The vessel will support Siemens Gamesa’s full service agreement for the Formosa 1 offshore wind project. Penguin International built the SATV at its shipyard in Singapore and delivered it at the beginning of […]

  • 9 October 2019
    Wind Farm Update

    All 20 Siemens Gamesa 6MW turbines have been installed at the Formosa 1 Phase 2 offshore wind project in Taiwan. To remind, jack-up vessel Seajacks Zaratan installed the first turbine at the project site 6km off the west coast of the Miaoli district in the Taiwan Strait in July. Prior to commercial operation, each turbine goes through […]

  • 20 May 2019
    Operations & Maintenance, Vessels

    The construction of a Service Accommodation Transfer Vessel (SATV) and a Crew Transfer Vessel (CTV) which will service the Formosa 1 wind farm in Taiwan is well underway, BMT, the designer of the vessels, said. BMT has partnered with the Singapore-based Penguin Shipyard International (PSI) for the 36m SATV and the 26m CTV. The keel […]

  • 30 January 2019
    Vessels, Wind Farm Update

    The self-propelled jack-up Seajacks Zaratan is on its way to Vlissingen in the Netherlands to undergo mobilisation in preparation for the Formosa 1 Phase 2 offshore wind project in Taiwan. Seajacks Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 wind turbines on the 120MW wind farm in the Taiwan Strait. This is the first renewables contract for […]

  • 13 August 2019
    Wind Farm Update

    Jumbo has completed the transport of all transition pieces for the Formosa 1 Phase 2 offshore wind farm from Thailand to the Taichung Port in Taiwan. Jumbo Kinetic transported the 20 transition pieces in three shipments from CUEL Limited’s yard in Laem Chabang in Thailand to the Taichung Port. Additionally, Jumbo coordinated the fabrication of 12 grillages which act […]

  • 15 October 2019
    Grid Connection

    Correll Services has completed the subsea and land cable termination and testing works at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Correll Services was in charge of project documentation, export cable (HV & FO) jointing at the TJB and OSS, array cable terminations (HV & FO) on 22 assets, and post-installation testing from […]

  • 12 March 2021
    Contracts & Tenders, Operations & Maintenance

    CWind Taiwan is set to return to Formosa 1 offshore wind farm this spring to deliver Inspection, Maintenance and Repair services. The company will deploy its technician team and a crew transfer vessel (CTV) to carry out the work on 22 of the Taiwanese wind farm’s turbines. Formosa 1 started commercial operation on 27 December […]

  • 11 September 2018
    Business & Finance, Operations & Maintenance

    Australia-headquartered Neptune and the Taiwanese subsea services company Global Aqua have formed a partnership to jointly work on offshore wind projects in Taiwan.