300 results found for 'GE Haliade-X '

300 results found for 'GE Haliade-X '
Order results by

A list of search results

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 3 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    SSE has revealed that the completion of Dogger Bank A, the first of the three phases of the UK’s Dogger Bank Wind Farm, is projected for the second half of 2025, which is later than the previously expected first half of the year. In its interim earnings report released on 3 October, SSE said that […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 30 July 2024
    Cables, Grid Connection

    Tekmar Group has completed its role in the Dogger Bank A offshore wind farm by supplying essential cable protection systems (CPS) for the project’s inter-array cables. This month, Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, achieved a significant milestone with the installation of all inter-array cables at […]

  • 5 July 2024
    Business development, Industry, R&D, Research & Development, Technology

    The US-headquartered GE Vernova plans to install a prototype of its next-generation 15.5 MW Haliade-X offshore wind turbine in Gulen, Norway, following a NOK 331 million (approximately EUR 29 million) funding approval from Enova, a government-backed agency. The funds from Enova have been secured by Wergeland Group and Georgine Wind, which is owned by GE […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 2 October 2024
    Business & Finance, Supply Chain, Wind Turbines

    Some 900 jobs in GE Vernova’s offshore wind business unit could be lost as the company plans to downsize the business. “On September 19, we submitted a proposal to the GE Vernova European Works Council related to proposed changes in our Offshore Wind business globally. The proposal reflects industry wide challenges for wind and aims […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 14 August 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to participate in one of the upcoming offshore wind solicitations in New York with its 1,314 MW Community Offshore Wind project, one of the three cancelled earlier this year as GE Vernova dropped plans for the 18 MW Haliade-X wind turbine which was planned to be used in the projects. Community Offshore Wind […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 30 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The installation of transition pieces (TPs) is about to commence at Vineyard Wind 1, America’s first large-scale offshore wind farm. Beginning next month, DEME Group’s jack-up vessel Sea Challenger will begin placing TPs at 17 monopile locations in lease area OCS-A 0501. The campaign will continue through June 2024. The units are being manufactured by […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]

  • 24 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the remainder of the damaged blade […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 5 September 2024
    Business & Finance, Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    Invenergy Wind Offshore (Invenergy) has requested a delay from the New Jersey Board of Public Utilities (NJBPU) until late December for its proposed 2.4 GW offshore wind project near Long Beach Island. In a July filing with the board, the company, which is developing the wind farm together with energyRe, cited challenges in finding a […]

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 14 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seaway7’s vessels, Seaway Strashnov and Seaway Alfa Lift, have commenced the installation of monopile foundations and transition pieces (TPs) for Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. The monopiles and TPs, […]

  • 22 April 2024
    Authorities, Planning & Permitting, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The New York State Energy Research and Development Authority (NYSERDA) has cancelled three offshore wind projects with a combined capacity of over 4 GW due to ”technical and commercial complexities between provisional awardees and their partners”. In October 2023, NYSERDA provisionally awarded three offshore wind projects, subject to the successful conclusion of contract negotiations. These […]

  • 23 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vineyard Wind 1, America’s first large-scale offshore wind farm, has begun delivering energy to the New England grid from five of its planned 62 GE Haliade-X 13 MW wind turbines. The units are currently generating 68 MW of energy, enough to power 30,000 homes in Massachusetts, according to the developers of the project, Avangrid and […]

  • 26 April 2019
    Business & Finance

    GE Renewable Energy is holding a series of supply chain engagement events in the UK for its Haliade-X 12MW offshore wind turbine. The events are part of GE’s supply chain plan for the world’s most powerful offshore wind turbine and will welcome potential suppliers that have suitable products or services that could support its production. GE […]

  • 13 November 2019
    Technology

    GE Renewable Energy has signed a cooperation agreement with State Power Investment Corp (SPIC) to bring the Haliade-X 12MW offshore wind turbine to China. GE announced in March last year that it will invest more than USD 400 million to develop and deploy Haliade-X 12MW, the world’s most powerful offshore wind turbine. The first unit was installed […]

  • 17 December 2019
    Business & Finance

    Dutch energy company Eneco is set to purchase all the electricity generated by GE’s Haliade-X 12MW offshore wind turbine prototype. This was announced during the inauguration ceremony for the prototype held today, 17 December, at the port of Maasvlakte-Rotterdam. According to GE, the Haliade-X 12MW prototype set a new world record the past weekend by […]