  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vattenfall has chosen to put the 640 MW Kriegers Flak offshore wind farm on hold until further notice because the investment conditions in Sweden are not feasible at this time, according to the developer. Vattenfall said that the investment prerequisites for offshore wind in Sweden are currently not viable, and the company has therefore decided […]

  • 15 July 2024
    Contracts & Tenders, Fixed-Bottom, Planning & Permitting, Project Updates, Supply Chain

    Danish transmission system operator (TSO) Energinet has awarded EMD International and C2Wind with contracts for the assessment of wind conditions at the five new offshore wind areas for which the Danish government launched an auction in April. The offshore wind sites are North Sea I, Hesselø South, Kriegers Flak II North, Kriegers Flak II South, […]

  • 14 October 2024
    Authorities, Business development, Planning & Permitting, Research & Development

    The Danish Energy Agency (DEA) has adopted a plan for the future Kattegat and Kriegers Flak II offshore wind farms, following an environmental assessment and consultation feedback. The tender for the Kattegat and Kriegers Flak II offshore wind farms was launched in April 2024. The bid deadline is 1 April 2025. The winner of the […]

  • 1 October 2024
    Authorities, Fixed-Bottom, Planning & Permitting

    The Danish Energy Agency has adopted a plan for the North Sea I offshore wind area following an environmental assessment of the plan and the consultation responses. The area comprises two subareas, the first of which has been already put out to tender with three offshore wind sites offered. The plan, which describes the framework […]

  • 3 September 2024
    Business & Finance, Business development, Research & Development

    EDF Renewables, a subsidiary of EDF, has acquired 100 per cent of Shell Overseas Holdings Ltd.’s shares in West Sea Energy 1, which is exploring the development of a large-scale offshore wind project in South Korea. The France-based company acquired its first offshore wind project in South Korea, located in the southwestern county of Yeonggwang. […]

  • 22 May 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Iberdrola has contracted Van Oord for the installation of wind turbine foundations and the supply and installation of inter-array cables for the Windanker offshore wind farm that the Spanish renewable energy company is building in the German sector of the Baltic Sea. Under the contract, the Dutch offshore construction specialist will transport and install 21 […]

  • 22 April 2024
    Authorities, Business & Finance, Contracts & Tenders, Environment, Green Hydrogen, Industry, Outlook & Strategy, Planning & Permitting, Power-to-X, Supply Chain

    Denmark has opened a new offshore wind tender, the country’s largest ever, offering a minimum of 6 GW of new capacity spread over six wind farms, with the overplanting option allowing for 10 GW or more of new capacity to be added. The Danish Energy Agency published the tender for the wind farms located in […]

  • 19 January 2024
    Environment, Fixed-Bottom

    Vattenfall and its partners in the WIN@sea project are preparing to harvest the first seaweed grown at the Kriegers Flak offshore wind farm in Denmark. After the harvest, scheduled for this Spring, the seaweed will be analysed for its quality as a foodstuff. Win@Sea, including Vattenfall, Aarhus University, the Danish Technological University, the University of […]

  • 21 December 2018
    Contracts & Tenders, Vessels

    Vattenfall has contracted Van Oord for the transport and installation of the foundations for the Kriegers Flak offshore wind farm.

  • 9 August 2019
    Contracts & Tenders

    Bladt Industries has contracted the Danish ProCon Wind Energy for the electrical construction of the transition pieces for the Kriegers Flak offshore wind farm. The work is expected to begin around the third quarter of this year and to be completed in the second quarter of 2020. At the end of last year, Vattenfall contracted Bladt […]

  • 28 March 2017
    Authorities, Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    The European Commission has found support to be granted to the 600MW Kriegers Flak offshore wind farm in Danish territorial waters to be in line with EU state aid rules.

  • 18 September 2019
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited companies to pre-qualify for boulder clearance work on the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea. The clearance of boulders would be carried out on the seabed at 72 wind turbine locations. The clearance is to be carried out with a vessel with a grab, and possibly by […]

  • 27 August 2020
    Contracts & Tenders

    JDR Hartlepool has completed the manufacturing and load-out of inter-array cables for the Danish Kriegers Flak offshore wind farm, the company reported via social media. Vattenfall awarded JDR with the inter-array cable contract in 2019. The company is supplying 170 kilometres of 33 kV cables for the 72-turbine of offshore wind farm. The inter-array cables […]

  • 19 May 2022
    Authorities, Wind Farm Update

    The Swedish government has granted a construction permit to Vattenfall for the Kriegers Flak offshore wind farm. Located in the south of the Baltic Sea some 30 kilometres off Trelleborg, Kriegers Flak is one of Vattenfall’s Swedish offshore wind projects that has come the furthest in its development. Vattenfall’s application covers 40 to 50 wind […]

  • 6 July 2015

    Energinet.dk has hired LIoyd’s Register for work on Kriegers Flak offshore wind farm. According to the contract, LIoyd’s Register is to certify offshore platforms which will hold the equipment needed for the connection of the Kriegers Flak offshore wind farms and the equipment needed for the offshore inter-connector Kriegers Flak Combined Grid Solution (CGS) between […]

  • 19 February 2018
    Grid Connection, Wind Farm Update

    Jan De Nul has installed the first of the two gravity-based foundations that will support the offshore substations on the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea.

  • 29 April 2021
    Business & Finance, Wind Farm Update

    The Kriegers Flak offshore wind farm in the Baltic Sea, where half of the turbines have been installed so far, is already generating electricity for Danish households and has contributed to Vattenfall’s Q1 2021 results. The developer reported a decrease in electricity generation in the first quarter of the year as a result of lower […]

  • 1 August 2019
    Vessels, Wind Farm Update

    Vattenfall has awarded Jan De Nul with a contract to provide a wind turbine installation vessel for the 605MW Kriegers Flak offshore wind project in the Danish Baltic Sea. The contract covers the supply of a wind turbine installation vessel for the transport of wind turbine components, and the support of the installation works of […]

  • 9 January 2018
    Ports & Logistics, Vessels, Wind Farm Update

    A barge carrying two gravity based foundations (GBFs) for the high voltage station of the Danish 605MW Kriegers Flak offshore wind farm has left the port of Ostend, Belgium.

  • 6 September 2021
    Wind Farm Update

    His Royal Highness the Crown Prince of Denmark, together with Danish Minister for Industry, Business and Financial Affairs, Simon Kollerup, has inaugurated Vattenfall’s 604 MW Kriegers Flak offshore wind farm. With 72 Siemens Gamesa 8.4 MW wind turbines and a capacity corresponding to the annual energy consumption of approximately 600,000 Danish households, Kriegers Flak is Denmark’s […]

  • 14 December 2017
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Vattenfall has chosen Klintholm Harbour in Denmark as its base for the servicing and maintenance of the 605MW Kriegers Flak offshore wind farm.

  • 23 May 2019
    Wind Farm Update

    Rostock-based EEW Special Pipe Constructions GmbH has started manufacturing the monopiles for Vattenfall’s 605MW Kriegers Flak offshore wind farm. The first pipe for the Danish offshore wind farm was made in the Rostock production site this May. By September 2019, all 72 monopiles will have been produced and coated, according to the company. In spring […]

  • 4 May 2018
    Grid Connection, Vessels, Wind Farm Update

    Heavy lift vessel Rambiz has installed the Kriegers Flak substation topsides in the Danish Baltic Sea, Energinet reports.

  • 3 November 2015
    Contracts & Tenders

    The preliminary tender specifications for Kriegers Flak offshore wind farm are delayed, the Danish Energy Agency (DEA) has informed. The tender material was scheduled to be published in October 2015, but the DEA said it now expects to publish the tender material in mid-November 2015. The agency published the Q&A on technical matters for Kriegers Flak […]

  • 19 November 2019
    Wind Farm Update

    EEW Special Pipe Construction has completed steel construction on all of the monopiles for Vattenfall’s Kriegers Flak offshore wind farm at its plant in Rostock, Germany. 72 monopiles are now structurally ready and the next step is to coat the units, some of which are up to 65.6 metres long. This work should be completed […]

  • 22 January 2021
    Authorities, Grid Connection, Wind Farm Update

    On 21 January, the Danish Energy Agency (DEA) granted an electricity production permit and issued an electricity production license to Vattenfall for the Kriegers Flak offshore wind farm in Denmark. The permit is valid for 25 years from the time when the first electricity is delivered from the offshore wind farm to the grid. The […]