85 results found for 'Ostwind 2'

85 results found for 'Ostwind 2'
Order results by

A list of search results

  • 7 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    First Vestas V174-9.5 MW turbines have been installed by Fred. Olsen Windcarrier’s jack-up vessel Blue Tern at the Baltic Eagle offshore wind farm in Germany. According to the AIS data available online, the vessel Blue Tern is currently in the Port of Rønne, Denmark, for the next loadout of wind turbines which will be installed […]

  • 10 July 2024
    Business & Finance, Grid Connection, Offshore Platforms

    Dutch engineering company Iv has designed more than a quarter of all offshore wind platforms in the European Union, the company said on 9 July, citing offshore wind statistics from a WindEurope report. Of the 19 GW of offshore wind energy the EU had installed at the end of 2023, Iv has worked on offshore […]

  • 23 May 2024
    Business & Finance, Grid Connection, Manufacturing, Offshore Platforms, Supply Chain

    Dutch company HSM Offshore Energy has entered into a long-term lease agreement with its compatriot Hollandia to use its Stormpolder yard in Krimpen aan den IJssel. The move is part of HSM Offshore Energy’s expansion plans and the growing order book, according to the company, which has several offshore wind and offshore grid projects in […]

  • 18 March 2024
    Business & Finance, Business development, Fixed-Bottom

    Abu Dhabi-based Masdar has achieved close on the financing of its 49 per cent shareholding in the 476 MW Baltic Eagle offshore wind farm in Germany. According to Masdar, the total lending package amounted to EUR 488 million, with participation from ABN AMRO, Credit Agricole CIB, ING, Santander, and Siemens Bank. The Baltic Eagle offshore wind […]

  • 26 February 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola Deutschland and O2 Telefónica have signed a long-term power purchase agreement to supply renewable power from the 476 MW Baltic Eagle offshore wind farm in the German Baltic Sea. Under the 15-year agreement, Iberdrola will supply 3,000 GWh of renewable energy to O2 Telefónica from the Baltic Eagle offshore wind project, starting in 2025. […]

  • 19 November 2020
    Grid Connection

    50Hertz has begun onshore cable activities near the Lubmin substation of the Ostwind 2 grid connection project in Germany. According to 50Hertz, specialized companies started using the so-called cable train for the 3km long onshore connection between the landing site at Greifswalder Bodden and the Lubmin substation. The transmission system operator added that works on […]

  • 2 October 2019
    Grid Connection

    50Hertz and Parkwind have signed a Memorandum of Understanding (MoU) to collaborate on the technical aspects of the Ostwind 2 grid connection project in the German Baltic Sea. The essential aspects of the MoU include specific agreements for the development, procurement, construction and operation of the shared offshore platform, Ostwind 2, covering basic technical details and […]

  • 29 June 2021
    Grid Connection

    German transmission system operator for the Baltic Sea, 50Hertz, has pulled in the land cables for the Ostwind 2 offshore grid connection. The Ostwind 2 land cables have now been installed underground over a distance of three kilometres from the landing point, where the sea cables meet the mainland, to the Lubmin transformer station. Using […]

  • 26 November 2018
    Contracts & Tenders, Grid Connection

    Boskalis and NKT have secured export cable contracts by 50Hertz for the Ostwind 2 offshore grid connection in Germany.

  • 21 July 2021
    Grid Connection

    50Hertz has reported that new transformers for the onshore substation for the Ostwind 2 offshore grid connection project have been delivered. The substation in Lubmin was first expanded in size and, with the new transformers, its transmission capacity is now being expanded. Preparatory work for connecting the transformers is currently taking place, including the installation […]

  • 12 March 2021
    Grid Connection

    The first cable section for the Ostwind 2 offshore grid connection was installed in the German part of the Baltic Sea in recent weeks, the transmission system operator 50Hertz said. In the coming months, further cables will be laid in individual sections along the 90-kilometre-long route. The work is being carried out by a consortium […]

  • 4 June 2021
    Contracts & Tenders, Grid Connection

    German offshore transmission system operator (TSO) 50Hertz has issued a tender seeking a provider of the 220 kV submarine and onshore cable system for the Ostwind 3 grid connection. The selected party will be in charge of the design, engineering, construction, installation, handling and commissioning of the cable system that will connect the onshore substation […]

  • 21 April 2021
    Grid Connection, Vessels

    NKT’s new cable barge NKT Agrippina has been loaded with a cable section for the offshore wind connection project Ostwind 2 in the German part of the Baltic Sea and will soon set out on its maiden trip after being christened on 20 April. The vessel has been specially designed to transport offshore power cables […]

  • 20 December 2023
    Cables, Fixed-Bottom, Foundations, Grid Connection, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Van Oord has completed the installation of all foundations and inter-array cables at Iberdrola’s Baltic Eagle offshore wind farm in the German sector of the Baltic Sea. The heavy-lift installation vessel Svanen installed the final monopile in September and the company has now put all the transition pieces (TPs) in place. The TPs were installed […]

  • 14 April 2021
    Contracts & Tenders

    German offshore transmission system operator (TSO) in charge of the Baltic Sea infrastructure, 50Hertz, has opened a tender for unexploded ordnance (UXO) operations on the cable route of the Ostwind 3 project. The work scope encompasses provision and operation of all assets necessary for the UXO campaign works, including reporting and interfacing with the employer […]

  • 10 December 2021
    Grid Connection, Wind Farm Update

    The second of the three 220 kV export cable systems for the Ostwind 2 project in the German Baltic Sea has been laid, 50Hertz Transmission GmbH said. This brings the connection of the Baltic Eagle offshore wind farm another step closer, the German transmission system operator said. The third and final cable is to be […]

  • 23 September 2020
    Environment, Grid Connection

    50Hertz has completed UXO clearance at the Ostwind 2 grid connection project in the German Baltic Sea.  The project comprised unexploded ordnance recovery at the subsea cable routes that will connect the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the German high voltage grid. Activities were completed between the landfall near Lubmin and the […]

  • 15 January 2019
    Contracts & Tenders, Grid Connection, Operations & Maintenance

    The Denmark-based Peter Madsen Rederi (PMR) has won a contract by 50Hertz to provide boulder clearance at the Ostwind 2 grid connection project in the German Baltic Sea.  The project comprises boulder clearance and extensive survey works at the three cable routes which will connect the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the German […]

  • 9 November 2021
    Grid Connection, Wind Farm Update

    The final section of the second of the three 220 kV export cable systems for the Ostwind 2 project is being laid in the German Baltic Sea, 50Hertz Transmission GmbH said. Around 170 kilometres of export cables have been laid at sea and on land over the past months to connect two offshore wind farms […]

  • 20 July 2022
    Grid Connection, Wind Farm Update

    Transmission system operator 50Hertz has announced that the Arcadis Ost 1 offshore substation has been connected to the German extra-high voltage grid after the 220 kV submarine cable required for this was pulled into place on the platform over the past few days. Final assembly and commissioning works will now follow. “We are very proud […]

  • 15 June 2022
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Parkwind and 50Hertz have installed the offshore substation for the 257 MW Arcadis Ost 1 offshore wind farm in the Baltic Sea. The 2,380-tonne, 30-metre high offshore substation was installed by the Scaldis crane ship Gulliver on its monopile foundation at the project site, located around 19 kilometres east of Rügen island in Germany. The […]

  • 1 June 2018
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    50Hertz Transmission GmbH has issued a tender for boulder removal services along the submarine export cable routes between the offshore wind farms in the German Baltic Sea and the landing point in Lubmin.

  • 23 February 2023
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors has installed the offshore substation topside for Iberdrola’s Baltic Eagle offshore wind farm in Germany. The substation topside, which was completed last month, was installed by Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Thialf. The jacket foundation had been placed on the construction site in October 2022. The installation involved the heaviest lifting […]

  • 5 December 2023
    Project Updates, Wind Farm Update

    The Arcadis Ost 1 offshore wind farm is now supplying its full capacity to the German electricity transmission grid, according to the transmission system operator (TSO) 50Hertz. 50Hertz built the submarine and onshore cable connection to the Lubmin substation and worked with the wind farm operator Parkwind to construct the offshore platform. Parkwind’s 257 MW […]

  • 7 May 2020
    Business & Finance, Grid Connection

    Eurogrid GmbH, the parent company of 50Hertz, has issued its debut green bond in the amount of EUR 750 million, which will finance the Ostwind 1 and 2 grid connections in Germany. The corporate bond with a term of 12 years and an interest rate of 1.113% was issued on the regulated market with the […]

  • 21 December 2018
    Business & Finance

    Boskalis and German SPIE SAG Group have entered an agreement under which Boskalis will acquire the offshore cable installation activities and assets of Bohlen Doyen.